Landowner guide

What should an owner check before describing backup generators as permitted?

An existing facility with backup generators may interest a data center user, but the presence of equipment or an air permit does not establish coverage for a proposed reuse. Compare the facility’s records with the actual permit and ask Virginia’s Department of Environmental Quality (DEQ) about changes before describing the site as permitted for a new plan.

The short answer

Collect the issued air permit, amendments and relevant correspondence, then compare them with a current equipment list and the proposed use. Ask the DEQ regional air permit manager whether the proposed generators, operating pattern or other changes require review or a permit action. Share verified documents privately with qualified parties and describe unresolved questions accurately.

Start with the issued documents

Gather the current issued air permit and amendments, equipment records, operating and maintenance records, and correspondence with DEQ. Identify the permitted facility and permit holder and ask the current operator or environmental adviser to reconcile the records with the equipment actually present. Check the permit conditions and status rather than relying on a marketing summary or an old application.

DEQ publishes a dated list of issued data center air permits with registration or application numbers, issuance dates, program types and regional offices. The list can help locate a record, but a listing alone does not establish current coverage for a particular proposal. Contact the regional air permit manager for individual permit questions and request missing information from DEQ as needed.

Illustration of a land parcel and surrounding landscape

Compare the equipment and the proposed use

Prepare a private comparison of the existing equipment list and issued permit, including any additions, replacements or differences in intended operation. For each generator, match the site and unit ID, nameplate rating, fuel and intended emergency and test hours to the permit’s unit list, applicable operating limits and logs; label it installed, proposed or to be removed. Check the permit’s actual wording, flag missing fields and do not assume every permit has the same limits. Ask the proposed user for a description of the reuse and expected changes, and flag unknowns for DEQ. Have a qualified environmental professional assess the relevant conditions and other applicable requirements.

Virginia DEQ’s air permit page explains that minor new source review can apply to a new source or a project involving additions, replacements or modifications of emissions units when applicable requirements are met. Virginia’s applicability rule includes exemptions, and an exemption from minor new source review does not remove other applicable requirements. Whether a particular change needs a permit action depends on the facts and applicable rules; the fact that a building previously had generators is not a blanket approval for a different configuration or use.

Ask DEQ about data center use before committing

Provide the regional air permit manager with the permit documents, equipment comparison and proposed change. Ask whether the existing authorization covers it, whether a modification or other review is needed, what information DEQ needs and when an application must be submitted. Record the response and review any formal determination or permit action with your adviser.

DEQ’s 2025 Data Center Air Permit Guidelines address data centers subject to Virginia’s minor new source review rules and note that major-source programs can carry additional requirements. They also discuss backup power and emergency classifications. DEQ’s 2026 generator permitting guidance updates presumptive controls for certain data center diesel generators for applications received on or after July 1, 2026. Ask DEQ which current guidance and requirements apply to the actual proposal; guidance and existing permit conditions are not interchangeable.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Describe the site accurately in a transaction

Before an option, lease or sale, have counsel address access to records, responsibility for applications and costs, timing, and what happens if a proposed change needs new authorization. DEQ’s construction guidance distinguishes general building work from construction associated with an emissions unit that requires a permit. Ask DEQ before beginning work if the distinction is uncertain.

Describe the facility as having an identified permit only after checking its status and scope; identify proposed changes as subject to review where appropriate. Sunland welcomes land and existing project inquiries nationwide. Share the location and your relationship to the property, and provide permits and sensitive equipment records privately when requested.

Questions landowners ask

Does an existing generator permit cover a new data center use?

Not automatically. The issued permit, actual equipment and proposed operations all matter. Ask the DEQ regional air permit manager to review the proposed changes.

Does a facility appearing on DEQ’s issued permit list prove that a proposal is approved?

No. The dated list helps identify issued permits. Review the actual permit and amendments and confirm the current status and proposed use with DEQ.

Are emergency generators exempt from all air requirements?

Do not assume so. DEQ distinguishes emergency and non-emergency operation and explains that some engines may be subject to federal rules even if exempt from permitting. Ask DEQ about the specific equipment and operation.

Sources & further reading

Sources checked 2026-11-15. Local rules and program details can change. Check the requirements for the actual project.