Ask what the utility document actually says
A preliminary inquiry, application or study request is evidence of a request, not proof that Dominion has agreed to serve a specified load by a specified date. A study or utility response can narrow the questions, but read its assumptions, date and conditions. Ask who made the request, which site and phase it covers, the requested megawatts, and whether the utility has identified a service approach or schedule.
An executed electric service agreement is a different kind of evidence: it can show that Dominion and its customer have agreed to terms for service. Have counsel check the parties, site, contracted demand, ramp, effective date, conditions, termination rights and any changes. Ask whether the buyer under your land option is the utility customer or has a documented relationship to that customer. An agreement may be confidential; request a written, appropriately redacted status confirmation or permit your attorney to review it privately rather than asking for customer-sensitive material in an initial inquiry.
Neither an inquiry nor a service agreement establishes that all infrastructure and approvals are complete, that power is available now, or that a particular land purchase will close. Dominion says site-specific power plans depend on factors including grid conditions, rights of way, permits and regulatory filings. Ask what remains outstanding and who controls the next step.

Understand the large-load tariff without assuming it applies
In its November 25, 2025 order, the Virginia State Corporation Commission directed Dominion to implement a GS-5 rate class effective January 1, 2027. The order describes the class generally as customers with measured or contracted demand of at least 25 megawatts on a contiguous site and a measured or expected load factor of at least 75%. It is not a rule for every data center or every Virginia utility. Ask the utility and the customer’s advisers to identify the current tariff and any applicable exceptions for this customer and site.
For each phase, ask what the applicable service agreement and current tariff require: contracted demand, any ramp, payments, collateral, conditions to service and consequences of termination. Ask what has actually been signed or paid and what remains contingent. An agreement can reflect a customer commitment without establishing that the infrastructure is complete or that service is available now.
These are obligations between the utility and its customer. An option extension fee is a separate payment negotiated with the landowner. Do not assume that collateral was posted or a utility payment made merely because the tariff provides for it, or that it will be paid to you.
Compare the extension phase by phase
Make a simple schedule for each parcel or phase: acreage, current option expiration, purchase price and closing date, extension length and fee, and evidence of utility progress. Check whether an extension for one phase also ties up later phases, whether the buyer can drop individual phases, and whether payments are credited against the purchase price or retained if a phase does not close.
Ask for specific milestones and a dated update: utility request or agreement status, studies and remaining conditions, zoning and permits, required substations and access, and the expected decision date for each phase. Consider whether the proposed fee fairly compensates for the time and loss of flexibility, whether it is refundable, when it is due, and what happens if a milestone is missed. A milestone should be verifiable and tied to a remedy in the written agreement, not just a hopeful schedule.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landReview the option before agreeing to more time
Your attorney can review the existing option and proposed amendment, including notice and exercise requirements, extension rights, deposits, phased closings, access and restoration, assignment, title and survey issues, and whether the buyer can terminate. Preserve current deadlines while that review happens; an extension request by itself does not change the signed agreement.
You can contact Sunland with the property location, approximate acreage, the broad status of the option and the decision you face. Share agreements or sensitive site and customer information privately only when appropriate. Sunland welcomes land and existing project inquiries nationwide.
Questions landowners ask
Does a Dominion inquiry reserve power for the property?
A preliminary inquiry alone does not establish a reservation or a delivery date. Ask the utility and project team what has been confirmed and what conditions remain.
Does a signed electric service agreement guarantee the land sale?
No. It is an agreement between the utility and its customer, subject to its terms. The purchase option and any amendment govern the land transaction.
Is a Dominion collateral payment the same as an option extension fee?
No. Utility collateral secures obligations to the utility when applicable. An option fee is governed by the land agreement and its negotiated terms.
Does GS-5 cover every Virginia data center?
No. The SCC’s November 2025 order describes a Dominion rate class with demand and load-factor criteria and an effective date of January 1, 2027. Confirm the current tariff and exceptions for the actual customer and site.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.