Put the proposed facilities on the property map
Ask the prospective developer for a dated plan showing the data center, substation pad and fence, proposed transmission corridor, road and gate locations, grading and drainage. Overlay it on a current survey or parcel map and note property lines, existing easements, utilities, buildings, wetlands and retained uses. Mark anything that crosses a boundary or conflicts with an existing use; a parcel map is helpful for a first discussion but is not a substitute for a survey or title review.
Ask whether the pad, corridor and access are preliminary or have been reviewed by the utility, and who would own, build and maintain each facility. A route drawn on a plan does not itself grant a right across your land or a neighbor’s land. The serving utility and project team must determine the actual configuration and required rights.

Understand the delivery point request
Dominion Energy Virginia’s Electric Transmission Facility Interconnection Requirements, Attachment 2, describe delivery point requests affecting its transmission facilities. Under that document, an electric distribution company initiates the request through Dominion’s Delivery Point Exchange; a landowner is not necessarily the requesting customer. Ask the developer and serving utility which process applies to the proposed service and who will provide each document.
For data center delivery points, the April 2026 attachment calls for a 30% site plan and a locality zoning conformance letter at the feasibility submittal stage. The plan includes the entire substation pad, dimensioned fence, entrance roads, proposed transmission corridors and approximate stormwater facilities. Dominion states that these submissions are used to infer a path to, or proof of, site control. The later development submittal calls for a final grading plan and required federal, state and local permits, which Dominion says are used to infer proof of site control. These are process-specific submissions; they do not replace the actual agreements or establish that every parcel or route is controlled.
Check gates, road rights and the corridor
Walk through the proposed route from a public road to the pad with the project team. Identify who owns each segment, where gates would sit, whether existing easements allow the intended construction and ongoing utility access, and whether additional rights or road improvements are needed. Ask about construction traffic, turning space, drainage, maintenance, emergency access and access outside normal business hours. Do not promise a crossing over a neighbor’s property without the necessary rights.
Compare the proposed transmission corridor with recorded easements and the landowner’s planned uses. Ask whether vegetation clearing, grading, equipment staging or restrictions outside the fenced pad are contemplated. Confirm dimensions and technical requirements with the utility for this proposal rather than treating an early drawing as final.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landSeparate a site plan from power and transaction commitments
A mapped pad or preliminary power plan does not reserve capacity or guarantee a delivery date. Dominion says its data center team develops site-specific power plans and that timing depends on factors including grid conditions, rights of way, permits and required regulatory filings. Ask the developer what the utility has confirmed in writing, what remains conditional and who bears the costs and delay risks.
Before signing an option, lease, easement or sale agreement, ask your attorney to identify the land and rights covered, investigation and extension periods, payment, access and restoration obligations, and what happens if permits, routes or service cannot be obtained. Share the location, approximate acreage and what land you may make available; Sunland welcomes land and existing project inquiries nationwide. Provide surveys, agreements and sensitive site plans privately when requested.
Questions landowners ask
Does a proposed substation pad prove power is available?
No. A plan identifies proposed space. The serving utility must evaluate the actual load and site, and any service, timing and infrastructure remain subject to the applicable process and conditions.
Does the landowner submit Dominion’s delivery point request?
Not necessarily. Dominion’s Attachment 2 says an electric distribution company initiates requests affecting its transmission facilities. Ask the project team and serving utility which process applies and who is responsible.
Does a site plan give the developer access across neighboring land?
No. Identify the owner of each route segment and have the relevant rights reviewed and secured by the responsible parties.
Do I need a completed site plan to contact Sunland?
No. Share the location and what you know about the property. A project-specific plan and further investigation would come later.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.