Verify which notice and date apply
The notice of intent (NOI) tells Virginia DEQ the applicant intends to submit a permit-by-rule application. Section 9VAC15-60-30 generally covers projects over five megawatts with a disturbance zone over 10 acres that do not otherwise qualify under Part III. Ask the developer for the DEQ project number and the dated notice. For a notice submitted on or before June 18, 2025, ask DEQ which timing rules apply to the project’s filing history.
Town Hall displays the date a public notice was posted and when that listing expires. For example, the revised Hera Solar listing shows an October 15, 2026 posting and a November 16, 2026 listing expiration. Use those dates to identify the public posting. To check the permit application deadline for your project, use the agency submittal record for the applicable notice and ask DEQ to confirm the date.
If the developer says it applied, request the dated application transmittal, proof of submittal and the latest DEQ status letter. If the developer is relying on an extension, request the written request, evidence of when DEQ received it and DEQ’s decision or current response. Ask DEQ to confirm the current deadline while any request is pending. Written authorization to construct and operate is a later agency decision.

Compare the latest layout with the notice
Ask the developer for the dated layout that went with the relevant filing and the current layout. Have it show the project acreage, disturbance zone, rated capacity and the part of your property it wants to keep under option. If a road, electrical route or work area has moved onto land you planned to keep available, check the proposed option exhibit as well.
Section 9VAC15-60-30 requires a new notice when a project change increases acreage or megawatts. For initial notices submitted after June 18, 2025, the rule requires at least 90 days between submission and the start of the required public comment period. Ask DEQ which notice and public comment dates apply to the latest layout before using them as milestones in your agreement.
| Record | What to check |
|---|---|
| Notice and dated layout | DEQ project number, agency submittal date, rated capacity and project acreage. |
| Application and latest agency correspondence | Submittal proof, layout version and current review or authorization status. |
| Extension request and agency response | When DEQ received the written request, its decision and the deadline it confirms. |
| Signed land option and exhibits | End date, extension notice and payment, acreage and any release or document-delivery terms. |
Review the extension terms for your land
Have Virginia counsel compare the agency timetable with the signed option. Check who can extend, how and when notice must be delivered, what payment is due and which land and access rights would remain under option. If you agree to more time, specify which dated DEQ record the developer should deliver and when.
Ask counsel what the agreement says if DEQ confirms the notice expired, the developer files a new notice or the revised layout drops some of your land. Check when you can commit the acreage elsewhere and whether any separate access rights or recorded option memorandum need a written release.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss a solar land proposal
Sunland welcomes inquiries from landowners and authorized representatives across the United States about land sales, leases and assignments of existing solar agreements. Share the general location and whether the developer is asking to extend the option or change its acreage. Keep signed agreements and detailed layouts for private review.
Questions landowners ask
Which date starts the 48-month period?
For covered notices submitted after June 18, 2025, use the date the notice was submitted to DEQ. Ask for the dated agency record and confirmation of the deadline for the notice that applies to the current project.
Does a developer get 36 more months by asking?
DEQ must receive the written request before the notice expires. DEQ may grant an additional 36 months. Ask for the agency’s decision and the date it confirms.
What happens to my land option if the notice expires?
Ask counsel to review the signed option and any related access agreement or recorded memorandum. Check the option’s deadlines, any permit milestones and the steps needed to release the land or clear the recorded interest.
Sources & further reading
Virginia’s solar permit-by-rule provisions and public notice records were checked November 22, 2026. Confirm the applicable notice, dates and status with DEQ and review the signed land option with counsel. Local rules and program details can change. Check the requirements for the actual project.