Identify the licensed premises and the departure
A specific license may cover a building, outdoor area or other defined location within a larger industrial property. Obtain the license, amendments, maps and dates of licensed activity, and identify the licensee and its radiation safety contact. Compare these with deeds, leases, parcel boundaries, building plans and the areas proposed for equipment, access and utility connections. A release record for one room or building does not necessarily establish the status of the entire parcel.
Ask the departing licensee and DOH what activities occurred, what areas may have been affected, and whether the relevant area has been surveyed, decommissioned or released. A historical license does not by itself prove contamination; missing records likewise do not establish that the site is clear. Request the actual documents rather than relying solely on a description in a lease or environmental questionnaire.

Understand the vacating notice and survey
Under WAC 246-221-270, a specific licensee must notify DOH in writing at least 30 days before vacating or relinquishing possession or control of premises that may have been contaminated by licensed activities. The rule also requires each licensee to permanently decontaminate premises before vacating or transferring them in accordance with chapter 246-246 WAC, then conduct a survey after decontamination. The department and the landlord or subsequent tenant or transferee must receive a copy of the survey no later than the date possession or control is relinquished.
Ask for the notice, survey report, location drawings and delivery record, as well as any DOH correspondence. Have a qualified radiation professional explain the report’s scope, dates, conclusions and relationship to the proposed footprint. The deadline belongs to the licensee; an owner should coordinate early enough for the licensee and DOH to address the actual departure and any required work.
Separate license termination from premises release
WAC 246-232-060 requires a specific licensee that decides to permanently discontinue all licensed activities to notify DOH immediately in writing and request termination, with required reports and information. The rule also addresses nonrenewal, disposition, surveys and decommissioning. Depending on the circumstances, a license can continue beyond its stated expiration for residual contamination until applicable criteria are met and DOH gives written notice of termination.
Obtain the disposition certification, survey and DOH written termination notice where applicable, and ask the licensee and DOH to explain any open items. Moving a source or receiving a transfer receipt addresses an item of material; it is not by itself a premises survey or evidence that the site meets release criteria. Conversely, license termination and the status of a particular part of a larger property should be checked against the actual documents and boundaries.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landCheck whether use is unrestricted or subject to controls
WAC 246-246-020 sets criteria for DOH to determine a site acceptable for unrestricted use, including a radiation dose criterion and reduction of residual radioactivity to levels as low as reasonably achievable. WAC 246-246-030 provides criteria for termination under restricted conditions, including legally enforceable institutional controls, financial assurance and a plan. A restricted outcome can carry continuing responsibilities that matter to an owner or operator.
Request the agency determination, approved plans, maps, recorded instruments and any monitoring, access or maintenance obligations. Counsel and the qualified radiation professional should identify who must maintain controls, whether they bind successors and whether the proposed construction and operation are compatible. Do not assume a restricted site is available for every industrial use or that a termination notice alone describes every obligation.
Fit the transaction and battery layout to the record
Overlay the proposed battery enclosure, transformer, roads, fence, drainage, staging and utility corridor on the licensed-area and survey maps. Include any off-site access or interconnection route. Ask the licensee, qualified professional and DOH as appropriate whether the records cover those areas and whether the proposed work conflicts with any controls or remaining decommissioning. Resolve uncertainties before setting access or construction dates.
For a sale or lease, counsel can address records delivery, access for the licensee and its contractors, responsibility for outstanding work and costs, schedule extensions, conditions to closing or possession, and a remedy if the required outcome is not achieved. A private agreement allocating costs does not itself alter regulatory duties. Preserve agency correspondence and final site plans with the property records.
Discuss the property with Sunland
Sunland considers land sale, lease and existing project inquiries across the United States. Share the location, acreage, ownership or authority to act, current use, known licensed history and status of any surveys or restrictions. Provide detailed reports and agency correspondence privately when requested. Sunland may place the parcel under contract and subsequently assign that contract to a specialist developer; an inquiry is not a commitment to buy, lease or fund decommissioning.
Questions landowners ask
Does an expired license mean the property is released?
No. Obtain the site-specific survey and release record and, where applicable, DOH’s written termination notice. A premises or portion of a site may be released separately from termination of the entire license. The rule provides for a license to continue beyond expiration in certain residual contamination circumstances.
Who gives notice before the premises are vacated?
WAC 246-221-270 requires a specific licensee to give DOH written notice at least 30 days before vacating or relinquishing control of premises that may have been contaminated by licensed activities.
Is a source removal receipt enough for the landowner?
It can document a material transaction, but it does not establish the premises survey, release status or license termination. Ask for the underlying premises and agency records.
Can a restricted site host a battery project?
That depends on the actual controls, proposed footprint and agency requirements. Have counsel and a qualified radiation professional review the documents and proposed work with DOH as appropriate.
Sources & further reading
Washington rules checked November 17, 2026. Requirements depend on the license, premises and circumstances; confirm the current record and applicable process with DOH and qualified advisers. Local rules and program details can change. Check the requirements for the actual project.