Identify the yard, vehicles and rights
Obtain the operator’s lease and amendments, registration and listed storage and redemption locations, available inspection records, site plan and current photographs. Identify the legal parcel, secure storage boundary, office, gate, vehicle circulation and any easements or access rights. Ask the operator which vehicles occupy the proposed project area and whether any are held by agreement, police authority or court order. Avoid publishing vehicle or owner information; the operator should manage individual records and applicable holds.
The landowner’s title or a contract to sell the land does not give the owner authority to remove, release, sell or abandon vehicles belonging to others. WAC 308-61-158 treats vehicles held by agreement, certain police holds or court order differently from abandoned vehicles. The operator must handle applicable release and processing requirements; a project deadline does not override a hold.

Test the battery footprint and yard access
Put the battery equipment, foundations, fence, gate, utility lines, drainage and clearances on a dimensioned plan. Add construction laydown, trenching, crane setup, deliveries and temporary fencing by phase. Compare each phase with the operator’s storage capacity and truck turning, public approach, office and redemption routes. Reserve workable access for customers and operator personnel, including after-hours releases; a gate controlled solely by the project could prevent access when it is needed.
RCW 46.55.060 requires personnel reachable 24 hours a day to release impounded vehicles within a reasonable time, and prescribes business-office hours and other redemption provisions. Agree on gate control, contact numbers, response arrangements and a contingency for construction closures with the operator. Preserve secure boundaries while allowing authorized access; do not assume a locked project gate alone satisfies either obligation.
Plan a compliant storage arrangement
WAC 308-61-158 requires vehicles in an operator’s custody to remain entirely within a secure area owned or operated under that registration. WAC 308-61-026 defines a secure area with fencing and a lockable gate, including specified height and wire requirements, while providing for certain waivers and enclosed-building treatment. Have the operator and agencies evaluate the actual remaining boundary, any replacement fence and access before changing the yard. Local zoning and other approvals may also matter.
If the operator proposes another lot, RCW 46.55.060 requires state patrol inspection and approval before an additional lot is used for vehicle storage and annual inspection and approval for continued use. The application must list secure storage and redemption locations; a separate business location requires a separate registration. Confirm the proposed site and any registration or filing changes with the agencies. WAC 308-61-158 prohibits the operator from charging for relocation between separate secure storage areas it owns or operates; it does not establish who pays project-related costs under the parties’ agreement.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landChoose a delivery path and document it
For a partial sale, survey the parcel and grant any agreed access or utility rights while retaining a functional approved yard; alternatively condition closing or possession on the operator’s lawful vacation of the sold area. For a lease, define an initially available footprint and phase later areas only after the operator completes the agreed steps. For an assignment, review the existing project and yard agreements, required consents and the assignee’s rights and obligations rather than assuming the assignment clears the site.
In each path, identify who obtains approvals and pays for fencing, relocation and delays; set milestones, evidence of inspection and approvals, a joint handoff inspection, and remedies or an extension or termination right if conditions are unmet. Require the operator to manage vehicles in its custody and preserve lawful access until handoff. Do not promise that the owner will deliver or remove third-party vehicles. Coordinate fire, building, zoning, utility and battery approvals separately. Sunland reviews land and existing project opportunities nationwide, including Washington battery storage sales, leases and assignments. An owner or authorized representative can share the location, acreage, operator arrangement and proposed footprint privately.
Questions landowners ask
Can the owner clear impounded vehicles to meet a closing date?
The owner should not assume authority over third-party vehicles. Coordinate with the registered operator, which must manage vehicles in its custody and any applicable holds or release procedures.
Can the operator move vehicles to another lot?
An additional lot must be inspected and approved by the state patrol before storage use, and vehicles in the operator’s custody must remain in a secure area owned or operated under its registration. Confirm the particular arrangement and any required registration changes with the agencies.
Can construction temporarily close the yard gate?
Construction must be planned around secure storage and lawful redemption access. Agree on an operational gate, contacts and a contingency with the operator before work begins; confirm the arrangement with relevant authorities.
Sources & further reading
RCW 46.55.060 and WAC 308-61-026 and 308-61-158 checked November 17, 2026 Pacific. Confirm the proposed storage and access arrangement with the operator, Washington State Patrol, Department of Licensing and applicable local authorities. Local rules and program details can change. Check the requirements for the actual project.