Map the land and the proposed movement
Obtain a scaled construction and clearing plan showing the parcel, trees, temporary work and access, and identify each proposed receiving site and the entire route, including any transfer point. Use WSDA’s searchable apple maggot map for the addresses, and check the legal boundaries in WAC 16-470-105 with WSDA where a route or parcel is near a boundary. Some counties are divided between quarantine and pest-free areas; a county name alone may not answer the question. The Okanogan quarantine boundary expanded effective March 23, 2026.
Ask the developer to identify the material by source and type, including fruit, branches, stumps, plant root balls, soil and mixed loads, and any changes in destination or route. A map does not itself authorize movement. WSDA can explain which requirements apply to the specific material and movement; a receiving facility must also agree to accept that material.

Identify regulated material without assuming all soil is covered
WAC 16-470-111 regulates specified fresh host fruit and categories including yard debris, organic feedstocks, organic materials and agricultural wastes as defined in WAC 173-350-100. Ask WSDA how the proposed clearing debris is classified. WSDA says facilities in quarantine areas cannot transport green waste into or through a pest-free area without a special permit, and waste facilities in pest-free areas cannot accept green waste from quarantine areas without a special permit. WAC 16-470-124 governs special permits for specified solid and organic waste movements; eligibility and conditions must be confirmed for the actual arrangement.
The apple maggot soil definition is narrower than all soil from a former orchard. It covers soil or growing medium in pots or on root balls of host plants from a quarantine area, and of nonhost plants within the drip line of host plants that have produced fruit. Do not assume loose former-orchard soil is automatically regulated under this specific definition or that a mixed load is unrestricted. Describe the actual material to WSDA and ask about any other applicable rules.
Get a facility and agency answer before release
The developer should identify the party responsible for requesting WSDA’s determination and any required permit or certificate, and provide the source, material, destination and route. Contact the WSDA Pest Program at pestprogram@agr.wa.gov; WSDA’s general assistance number is 360-902-1800. Ask which party must hold the authorization, whether it covers this material and route, and what documentation must accompany the movement. Leave handling and movement procedures to WSDA and the authorized operators.
Ask the named receiving facility to confirm in writing that it can and will accept the described material, estimated quantity and delivery dates, including any acceptance conditions and applicable authorization. A contractor’s choice of facility or a general assurance that debris can be disposed of is not a substitute. Obtain the relevant approvals and acceptance before release, retain copies, and require a new review if the source, material, route or destination changes. If authorization or acceptance is unavailable, pause the affected hauloff and agree on another lawful plan.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPut cost, timing and alternatives in the agreement
Review the deed, farm or orchard tenancy, existing access rights and the proposed solar agreement with counsel. Identify who may consent to tree removal, entry and possession, and obtain any required rights-holder consent. State the approved clearing limits and who directs subcontractors. Make off-site movement conditional on applicable agency authorization and facility acceptance; identify who obtains and pays for them, who bears hauling, disposal, rejected-load, delay and restoration costs, and what happens if requirements or the schedule change. Require notice, records and a completion check.
Compare the quoted cost and schedule for approved hauloff with an alternate footprint that avoids the trees or former orchard, postpones clearing, or leaves material in place where permitted and accepted by the owner and project. Have the developer and appropriate authorities assess site-specific land-use, fire, waste and other obligations before choosing on-site retention; it is not automatically allowed. Decide who pays for redesign, ongoing obligations and restoration, and whether delay affects rent, milestones or the owner’s use of the land.
Sunland welcomes solar land inquiries nationwide, including Washington. Share the location, acreage, existing uses and proposed clearing schedule, and provide maps and agreements privately as needed.
Questions landowners ask
Is all soil from a former orchard regulated by the apple maggot quarantine?
No. The specific WAC definition covers soil or growing medium in pots or on certain plant root balls, not all loose orchard soil. Ask WSDA about the actual material, any mixed load and other applicable rules.
Can the contractor take debris to a facility in a pest-free area?
Only if the applicable requirements are met. Confirm the material, route and any necessary WSDA authorization, and get the receiving facility’s written acceptance for the proposed load before release.
Can the owner simply leave the material on the property?
Possibly. Compare leaving it in place or changing the footprint with hauloff, but first confirm applicable local and state requirements, project constraints and any necessary rights-holder consent.
Sources & further reading
WSDA quarantine guidance and Washington Administrative Code provisions checked November 16, 2026. Confirm current boundaries, material classification and requirements with WSDA for the proposed movement. Local rules and program details can change. Check the requirements for the actual project.
- WSDA: Apple maggot quarantine and searchable map
- Washington Legislature: WAC 16-470-105, quarantine and pest-free areas
- Washington Legislature: WAC 16-470-103, definitions
- Washington Legislature: WAC 16-470-111, regulated commodities
- Washington Legislature: WAC 16-470-115, movement within Washington
- Washington Legislature: WAC 16-470-124, special permits
- WSDA: Apple maggot and green waste
- WSDA: Apple maggot program and special permit contact