Compare the historic footprint with the work
Search the address or parcel in Ecology’s Dirt Alert former orchard map and save a dated view. Its orange areas are based on historical aerial photographs and show approximate historic orchard locations. Not every historic orchard used lead arsenate, and orchards planted after 1950 are not included. A mapped boundary is a starting point, not a soil test or a precise construction limit.
Place the historic view beside parcel boundaries and the current layout, including panel areas, inverter pads, collector trenches, foundations, access roads, drainage, stockpiles and temporary staging. Ask where grading, excavation or imported or exported soil is proposed. Review aerials, farm records and interviews for areas that may have had different uses; a large parcel can have different histories across it.

Find records and plan site-specific sampling
Request existing environmental reports, laboratory results, cleanup plans, deeds and recorded environmental covenants from the owner and relevant agencies. Search Ecology’s cleanup database and ask about records not online. Have an environmental professional assess whether samples represent the proposed disturbance areas and depths, their age, analytical methods and gaps. If needed, develop a sampling plan for the site and proposed work; Ecology’s map also invites property owners to ask about free sampling.
Ecology identifies lead and arsenic as concerns from historic lead arsenate use. Other past operations may warrant different analyses. The appropriate investigation and response depend on actual conditions and proposed use. Ecology’s map lists cleanup levels of 20 parts per million for arsenic and 250 for lead; have the professional and Ecology determine applicable standards and the implications of the results rather than treating a map or a single sample as a site-wide conclusion.
Plan excavation and soil movement
Compare investigation results with the depth and location of each trench, pad, road and grading area. Ask the developer’s environmental professional to prepare a soil management approach before disturbance, addressing worker protection, dust and erosion controls, segregation, stockpiles, sampling, reuse or disposal, and tracking. Coordinate any offsite movement and receiving facility requirements with the relevant authorities and facility before hauling.
If a cap, covenant or cleanup plan exists, examine its exact boundaries and terms before driving equipment over it or excavating. Solar cables or foundations may cross a protective layer, so the project team should establish any required approvals and an acceptable design and repair or monitoring plan before work. An existing cleanup decision does not automatically authorize new disturbance.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landUse the right process for the project
Ecology publishes model remedies and a self-certification workflow for qualifying residential development on former orchard land. A solar facility has different exposure and construction patterns. Do not assume the residential forms or a particular remedy automatically apply; discuss the project with Ecology, local development staff and a qualified professional to determine the applicable cleanup and permitting path.
At Ecology’s West Valley Commercial Center Lot 3 example in Yakima, development addressed lead, arsenic and pesticide contamination with caps and an environmental covenant and operations and maintenance plan. Ecology issued a no-further-action determination, while restrictions and cap maintenance remain. This is an illustration of a site-specific commercial cleanup, not a prescribed solar remedy.
Put responsibilities into the agreement
Ask counsel and the project team to allocate who investigates, pays for sampling and cleanup, obtains approvals, handles excavated soil and maintains any remedy during operation and decommissioning. Address discovery of unexpected contamination, schedule changes, access for investigation, reporting and the consequences if the project cannot proceed. Review existing leases and other property obligations alongside the proposed solar agreement.
Sunland welcomes solar land inquiries nationwide. Describe the parcel location, your relationship to it and any known orchard history or soil records; share sensitive documents privately if requested.
Questions landowners ask
Does an orange orchard overlay prove contamination?
No. It identifies an approximate historical orchard footprint for screening. Site-specific records and appropriate sampling are needed to understand actual conditions.
Is a parcel outside the map automatically clear?
No. The map has limits, including its historical period and coverage. Review site history and consult a qualified professional about whether investigation is warranted.
Can a solar trench cross a former orchard cleanup cap?
That depends on the remedy, covenant and applicable approvals. Review the specific documents with Ecology and the project’s environmental professional before disturbing the cap.
Does Ecology’s residential self-certification automatically cover solar?
Do not assume it does. Ask Ecology and local permitting staff which process and requirements apply to the particular solar project.
Sources & further reading
Washington Ecology’s map, program guidance and commercial cleanup example were checked November 16, 2026. Site history, conditions, remedy and applicable requirements need site-specific review. Local rules and program details can change. Check the requirements for the actual project.