Map the working facility and the proposed battery footprint
Gather the site plan, product inventory, containment designs, inspection and spill records, leases and utility drawings. Identify the operator and owner, and map liquid tanks and secondary containment, dry fertilizer buildings, loading pads, sumps, pipes, truck turning areas and emergency access. Include the proposed battery equipment, access road, buried lines, grading and temporary construction staging, not just the fenced pad.
Wisconsin DATCP regulates bulk fertilizer and pesticide storage under ATCP 33. Dry and liquid products have different storage and pad requirements, and pesticide activity may involve additional rules. Ask the operator and DATCP which structures and activities are covered before treating a slab or apparently unused area as available.

Plan changes to containment before construction
If the dealer continues operating, preserve compliant storage and handling capacity and safe truck access throughout the work. Under ATCP 33.30, bulk fertilizer handling at a storage facility generally must occur over a mixing and loading pad, subject to specified exceptions. A replacement pad or containment system may need engineering, installation and inspection before the old area can be surrendered.
ATCP 33.10 requires the operator to file design specifications, a professional engineer’s signed compliance certification and the approximate start date with DATCP at least 21 days before constructing or substantially altering a covered structure. Substantial alteration includes changes that may affect containment or recovery; routine repair or maintenance and routine replacement of parts with like parts are excluded. The rule does not require DATCP approval of the proposed work, but the operator must comply with the chapter. Ask DATCP and the engineer whether the specific work triggers filing and what other requirements apply.
Separate removal from a discharge response
Taking a facility out of service is not itself proof of contamination or regulatory closure. Under ATCP 33.70, when a mixing and loading pad, sump or secondary containment structure used for liquid bulk fertilizer or liquid bulk pesticide leaks, is removed or remains out of use for more than five years, the operator must conduct an environmental assessment and file a written report with DATCP. The assessment addresses whether discharges occurred and their extent and severity, with sampling and analysis as necessary. Do not assume this specific trigger applies to every dry-only structure; discuss the proposed work and site history with DATCP.
A release is a separate issue. DATCP says spills that harm or threaten public health or the environment require cleanup, regardless of quantity. Its spill guidance also identifies circumstances requiring immediate reporting to the 24-hour Wisconsin spill hotline, 800-943-0003. If contamination is found, stop affected work and coordinate reporting, investigation and corrective action with the responsible parties, DATCP and environmental counsel. Do not assume that removing a pad or filing an assessment resolves a release.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landAgree on phased possession and evidence of delivery
A lease or sale should show which areas the developer may enter for surveys, which remain in fertilizer use, and when construction possession begins. With counsel, define milestones for moving product and equipment, completing replacement containment, any required filings or assessments, and preserving access for sampling or cleanup. Set responsibilities, costs, schedules, extensions and outcomes if a milestone cannot be met.
Document boundaries and access rights on a plan, including utility corridors and construction traffic. Coordinate environmental due diligence, title, local permits and emergency access before ground disturbance. Sunland reviews battery storage land and existing project opportunities nationwide. Share the location, acreage and known facility status; provide sensitive records privately if requested.
Questions landowners ask
Can the dealer keep operating during battery construction?
Possibly. The parties need a workable separation of construction and fertilizer operations, compliant containment and handling arrangements, and safe access throughout each phase.
Does every pad change need DATCP approval?
ATCP 33.10 requires advance filing for construction or substantial alteration of a covered structure, but does not require DATCP approval of the proposed work. Ask DATCP and an engineer about the specific change and any other applicable requirements.
Does removing a liquid fertilizer pad require an assessment?
ATCP 33.70 requires an operator assessment and written report when a mixing and loading pad, sump or secondary containment structure used for liquid bulk fertilizer or liquid bulk pesticide leaks, is removed or remains out of use for more than five years. A release may also require separate reporting and cleanup.
Sources & further reading
Wisconsin DATCP bulk containment, environmental assessment and spill guidance checked November 16, 2026. Requirements depend on the products, structures and work involved; confirm the proposed transition with DATCP and qualified advisers. Local rules and program details can change. Check the requirements for the actual project.
- Wisconsin Administrative Code: ATCP 33, fertilizer and pesticide bulk storage
- Wisconsin DATCP: Agricultural chemical storage and containment
- Wisconsin DATCP: Fertilizer and containment program information
- Wisconsin DATCP: ATCP 33 environmental assessment guidance
- Wisconsin DATCP: Agricultural chemical spills
- Wisconsin DATCP: Spill reporting guidance