Identify the facility, permit and equipment
Obtain the construction and operation permits, amendments or registration or general permit coverage letters, the FID number, inspection correspondence, emissions reports, compliance certifications and fee records. Identify the legal permittee, property owner, operator and responsible official; they may be different people or entities. Ask the DNR air compliance inspector to help confirm the permit status and any outstanding requirements.
Inventory emission units and controls, such as boilers, generators, process equipment and stacks, against the permit and site plan. Record what will remain, operate, be disconnected, removed or sold. The battery layout and access arrangements should account for retained equipment. A battery project may need its own review if equipment or operations change; ask DNR about applicable construction and operation requirements before making changes.

Plan a change in responsibility for a continuing source
DNR says facilities holding air permits must notify its Air Program of changes in ownership, facility name, parent company or responsible official. For an ownership or name change, send the FID, old and new names or owners and the change date on or as soon as possible after the change. DNR asks for a written agreement between current and new permittees stating a specific date for transfer of permit responsibility, coverage and liability. The responsible official should send or be copied on the notification. Check the actual permit for its specific deadlines and conditions; some registration permits require notice within 30 calendar days.
Coordinate that date with closing and actual operating control, and ask DNR how to handle any gap or delayed closing. Agree who monitors, reports, maintains controls, pays fees and retains records before and after the date. A private allocation of costs does not by itself change regulatory duties. If the responsible official changes, DNR must make that change; provide the requested old and new contact information as soon as possible.
Check the permit type with DNR
DNR says a facility with registration or general permit coverage receives a new coverage approval letter reflecting a facility name change. For a source-specific operation permit, the facility name and responsible official are normally updated at renewal. If the permit does not expire or an earlier update is desired, the facility can apply for an administrative permit revision using Form 4530-100. Ask DNR which steps apply to this permit and keep the submitted agreement, notice and agency response with the closing records.
An option or lease for battery development does not necessarily change who owns or operates the existing source. Describe the actual transaction and the parties’ intended control to DNR before assuming a transfer is appropriate. If the owner retains the permitted equipment or operations on part of the property, document access and the division of responsibilities and ask DNR how the proposed arrangement affects the permit.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landUse the closure path if operations will end
DNR distinguishes facility closure from administrative ownership changes. It asks to be notified on or soon after closure and cessation of operations, including the closure and cessation dates, intentions for equipment and emission sources, and a contact afterward. Notify the designated compliance inspector and send the letter to the operation permit processor as directed by DNR.
DNR says permits remain in effect with the facility after closure or sale unless formally revoked. Keeping them active can preserve an option to resume operations, but brings continuing management, reporting and fees. DNR recommends requesting revocation when equipment is scrapped or removed and sold. Revocation cannot be reversed; a later restart or sale may require a new permitting process. Confirm remaining reports, disposal steps and timing with DNR, and do not treat revocation as resolving contamination or remediation obligations.
Put the decision into the transaction
Before signing, have environmental counsel and advisers map the permitted equipment and responsibilities against the land and project schedule. Make the agreement address access, records, costs, pending compliance matters and what happens if closing or equipment removal is delayed. Separate air questions from other permits, waste handling and site cleanup, which may have their own requirements.
Sunland welcomes land and existing project inquiries nationwide. Share the property location, approximate acreage, your relationship to it and the permit issue; provide permit records privately if requested.
Questions landowners ask
Does selling the land cancel the air permit?
No. DNR says existing permits remain in effect with the facility even after closure or sale unless formally revoked. Determine who will be responsible and follow the applicable notification or closure process.
Does a battery site-control agreement require an air permit transfer?
Not necessarily. An option or lease may leave the existing source under the same owner and operator. Describe the actual control and planned equipment to DNR and check the permit before deciding what action is needed.
Can a revoked permit be turned back on later?
DNR says a revoked permit cannot be reactivated. A future restart may require a new permitting process, so discuss equipment plans and the consequences before requesting revocation.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.