Landowner guide

What should a Wisconsin forest owner check before agreeing to a battery storage site?

If a battery storage developer proposes using land enrolled in Wisconsin’s Managed Forest Law (MFL), compare the full project footprint with the MFL order before agreeing to a site. Ask your assigned Department of Natural Resources (DNR) tax law forestry specialist how the proposal affects the enrollment and whether withdrawal is available.

The short answer

Gather the MFL order and management plan and overlay the proposed battery equipment, access, cables, clearing and construction areas. Ask the specialist which land and uses would require withdrawal and whether the remaining enrolled land would qualify. Request a withdrawal tax estimate from the Wisconsin Department of Revenue (DOR) before deciding how to proceed.

Map the proposal against the MFL order

Collect your order of designation, enrollment map, management plan, parcel records and any prior withdrawal documents. Ask the developer for a drawing showing battery containers or equipment, inverters, transformers, fencing, roads, underground cables, grading, tree clearing, staging and any off-site connection. Compare the proposed permanent and temporary work with the enrolled boundary and mark uncertainties.

Give the drawing, order and proposed schedule to your assigned DNR tax law forestry specialist. Ask which areas and activities affect eligibility, whether the site or a different footprint would require withdrawal, and what records or maps are needed. Use DNR’s Forestry Assistance Locator to find the specialist for the property.

Illustration of a land parcel and surrounding landscape

Do not assume a battery installation is an allowed storage building

DNR says buildings used exclusively for storage are allowed on all MFL entries; rules for buildings also differ by designation date. A battery energy storage installation includes equipment and an industrial use, and its name alone does not establish that it qualifies as a building used exclusively for storage. DNR’s eligibility criteria also say land may not be developed for commercial recreation or industry.

Describe the actual equipment, enclosure, use and associated work to the specialist and ask for a site-specific determination. Do not treat the storage-building allowance as approval for the battery project or assume that removing only the equipment pad will resolve all effects on the enrollment.

Check withdrawal and the land that remains

DNR describes an option to withdraw one area of 1 to 5 whole acres per MFL parcel during a 25-year enrollment, or twice during a 50-year enrollment, for construction or another use. Ask the specialist whether that option applies to this order, prior withdrawals and proposed footprint, and what other process may apply if it does not. Local zoning may impose a larger minimum construction site.

DNR says a withdrawal will not be approved if the remaining land fails its eligibility criteria. Requirements depend on the order, including productive forest, configuration and acreage. Work with the specialist on the withdrawal map and review both the withdrawn area and remaining enrollment before signing. Discuss the filing deadline and effective date as well as the project schedule.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Estimate the cost and set responsibilities

DNR says it cannot calculate a withdrawal tax estimate; request one from DOR for a fee using Form PR-296. DNR describes a withdrawal tax and a $300 fee for the construction withdrawal process. Ask the specialist about the applicable process and any exception for your facts; do not assume a project or proposed route qualifies for an exemption.

DNR’s withdrawal FAQ says the withdrawal tax and fee must be paid and the withdrawal order issued before beginning practices inconsistent with MFL. Review an option, lease or easement with your attorney and address who pays for mapping, withdrawal, taxes and project changes if the proposed footprint cannot proceed. Sunland welcomes land and existing project inquiries nationwide. Share the location, approximate acreage and your relationship to the property; provide MFL records privately if requested.

Questions landowners ask

Does a battery storage project automatically qualify as an MFL storage building?

No. DNR allows buildings used exclusively for storage, but a battery installation and its associated land use need a site-specific review. Ask your tax law forestry specialist.

Can I withdraw just the battery footprint?

Possibly, if the applicable withdrawal requirements are met and the remaining MFL land remains eligible. Discuss the full equipment, access and construction footprint and any prior withdrawals with the specialist.

Who estimates the withdrawal tax?

The Wisconsin Department of Revenue can provide an estimate for a fee using Form PR-296. DNR says its staff cannot calculate withdrawal tax estimates.

Sources & further reading

Sources checked 2026-11-15. Local rules and program details can change. Check the requirements for the actual project.