Identify the corridor and proposed work
Gather the parcel survey, title commitment, recorded easements and any railroad correspondence. Ask the developer for a preliminary drawing from the battery site to the proposed connection, showing where the cable would cross the corridor. Label uncertain boundaries and ownership. WisDOT provides a railroad property map as a starting point; confirm the property and controlling party before choosing a permit path.
Distinguish the electrical utility crossing from construction-vehicle access across tracks. WisDOT identifies a separate process for non-utility work or uses on its railroad property. If the property is privately controlled or ownership is unclear, ask the relevant railroad or property holder about its process instead of assuming the WisDOT utility permit applies.

Ask about the WisDOT utility permit
For utility work on WisDOT railroad property, WisDOT directs applicants to submit DT2036 with associated plans or drawings and the required fee to the appropriate listed regional railroad coordinator. Plans must include proposed heights, depths and capacities of utility installations or modifications. Ask the listed Trans 29 contact what documentation and coordination the particular cable design requires.
Ask the developer who will prepare and submit the application, communicate with the agency and affected railroad, and obtain any other permissions. An application is not approval, and neither a map nor a proposed route establishes electric interconnection capacity.
Make the route part of the agreement
Compare the crossing and cable route with the proposed site boundary and any easement exhibit. Ask whether the route requires land or rights outside the owner’s parcel and who will secure them. Review investigation access, survey work, restoration and payment for damage before work begins.
With your attorney, review the option, purchase or lease terms for crossing deadlines, costs, route changes, extension and termination rights, and what happens if the crossing cannot be authorized. The agreement and actual corridor records determine the owner’s position; do not assume the project can use a crossing merely because it appears on an exhibit.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPrepare for a site discussion
Bring the property location, approximate acreage, survey and any known corridor documents to a discussion with the developer. Ask for the proposed crossing point, the party handling the application, and the next agency question. Avoid treating a preliminary route as final engineering.
Sunland welcomes land sale, lease and existing project inquiries from owners and authorized representatives nationwide. Share the property location, acreage if known, your relationship to it and the railroad crossing question; provide documents privately if requested.
Questions landowners ask
Does a cable crossing need a WisDOT permit?
WisDOT says utility work on its railroad property requires a permit under Trans 29. Confirm who controls the specific corridor and ask the listed coordinator about the proposed work.
Does DT2036 authorize construction once submitted?
No. Submitting an application is not approval. Ask the coordinator about the review and any other permissions needed.
Is a vehicle crossing covered by the same process?
WisDOT identifies a separate process for non-utility work or uses on its railroad property. Ask about the actual access work and corridor.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.