Map the retained operation before agreeing to a footprint
Place the pond and its banks, fish barriers, inlet and outlet, pumps, pipes, wells, drainage, power, buildings and fish-handling areas on a scaled plan. Add the proposed array, fence, road, cable route, grading, stormwater features, staging and temporary construction areas. Check which land is owned, leased or subject to easements and identify the registered fish-farm operator and permittee. DNR lists ownership, lease or control of the land next to the waterbody by fish-farm owners among NR 19 permit eligibility requirements. Review any proposed change to that control with DNR.
With the operator, trace year-round routes for stocking, feeding, harvest, deliveries, equipment, emergency repairs and pond maintenance. Test vehicle turning and access at gates and across solar roads and cable corridors. A pond kept outside the leased or sold acreage can still be impaired if its access, water supply, drainage or electrical service is interrupted. Ask the developer to revise the plan where necessary and agree on how affected infrastructure will be protected or restored.

Read the fish-farm permit and registration separately
Obtain the current NR 19 permit, amendments, expiration and conditions, site diagrams, correspondence and DATCP fish-farm registration. DNR generally requires a natural waterbody permit for a DATCP-registered fish farm using a natural body of water for aquaculture, subject to applicable exemptions. A natural body includes a spring, stream, pond, lake or wetland historically present in a natural state, even if physically altered. DNR describes exemptions associated with certain other permits; ask the coordinator to confirm the status of this specific waterbody.
A waterbody licensed by DNR as a private fish hatchery on January 1, 1998 may be eligible for a grandfathered NR 19 permit. Otherwise, DNR says new use of a natural waterbody for fish farming is limited to freeze-out ponds and requires an initial permit. Do not assume a pond can be relocated or an existing permit replaced on the same terms. Discuss any proposed changes in facility, water connections or operation with DNR before committing to a layout.
Distinguish the solar deal from a fish-farm transfer
If the owner retains the pond and remains the fish-farm operator, an upland solar lease or partial sale does not necessarily transfer the fish farm. Provide DNR the proposed boundaries, access arrangements and identities of the landowner, operator and permittee, and ask whether the change requires action under the existing permit or other approvals. Do not assume that retaining the pond alone resolves those questions.
If the fish farm itself changes hands, DNR says an NR 19 permit transfer is required when property is sold. Its application also describes transfer when ownership or a leasehold interest in a fish farm changes. Form 3600-227 is used for an NR 19 application; ask the local DNR Fish Farm Environmental Permits Coordinator about the applicable transfer, supporting records and timing. DNR posts natural waterbody applications for public notice; it may grant an application without a hearing if no substantive written objection is received within 30 days after posting. Application is not approval.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landCoordinate the transaction and the approvals
Before signing, have Wisconsin counsel and the operator review the survey, title, existing leases, mortgages, easements and permit conditions. For a sale, reserve and record appropriate access and utility rights over the conveyed land and confirm the retained parcel has practical routes to the pond. For a lease, define the leased footprint and reserved rights, gate access, work notices, repairs and compensation for damage or interrupted operations. Include construction timing, drainage protection, insurance, restoration and decommissioning security.
Address who applies and pays for required approvals, the schedule, consequences of denial or delay, and who operates and maintains fish-farm facilities throughout closing or construction. An assignment of the solar agreement can introduce a new solar counterparty; require notice and specify continuing obligations and consent rights as negotiated. If the fish-farm ownership or leasehold also changes, separately confirm the DNR permit and DATCP registration steps. Private contract terms cannot substitute for agency approval.
Check other water and site requirements
A natural waterbody permit does not authorize every solar construction activity. Ask DNR and local authorities about waterway, wetland, stormwater, zoning and other approvals for the complete footprint, including roads and cable crossings. Water withdrawals, discharges or wells serving the fish farm may have separate requirements; identify them early and assign responsibility for maintaining service.
Sunland welcomes inquiries about Wisconsin solar land, sales, leases and existing projects, as well as opportunities nationwide. Share the location, approximate acreage, proposed solar area and whether the pond and fish operation will remain with you. Provide permits and sensitive site records privately when needed.
Questions landowners ask
Does selling upland automatically transfer the pond permit?
Do not assume it does. Identify what is sold and who will own and operate the fish farm, then ask the DNR coordinator how the proposed transaction affects the NR 19 permit. A fish-farm permit transfer is a separate agency process.
Can I keep operating the pond after a solar lease?
Possibly. Check the permit and registration, preserve practical access and services, and review the actual plan with DNR. The answer depends on the operation, agreement and applicable approvals.
Does a solar developer taking an assignment become the fish-farm permittee?
A solar agreement assignment does not by itself establish a fish-farm permit transfer. If ownership or a leasehold interest in the fish farm changes, consult DNR about its transfer process.
Sources & further reading
Wisconsin DNR program guidance and an NR 19 transfer application were checked November 17, 2026. Confirm the permit, registration and site-specific requirements with the appropriate agencies. Local rules and program details can change. Check the requirements for the actual project.
- Wisconsin DNR: Natural waterbodies and fish farms
- Wisconsin DNR: Natural waterbody permits for fish farms fact sheet
- Wisconsin DATCP: Fish farm registration
- Wisconsin DNR: Fish farming in Wisconsin
- Wisconsin DNR: Fish farm environmental permit coordinators
- Wisconsin DNR: Example NR 19 transfer application
- Wisconsin DNR: Changes at a business and property transfers
- Wisconsin DNR: Fish farm water diversion