California landowner guide

What happens to recycled irrigation water in a Woodland battery storage land deal?

A battery storage offer for part of an industrial property can affect existing recycled water irrigation even if the project does not need that water. Before signing, compare the proposed boundary with the approved use area, meter and lines serving the retained land.

Could my land work?

Obtain the City-approved recycled water records and map them against the sale or lease exhibit. Ask Woodland how the proposed ownership, subdivision, site use and operating arrangements affect service, and document access and maintenance for lines that must remain in place.

Map the service area before dividing the site

Locate the recycled water meter, valves, irrigation lines, irrigated areas and access routes on a plan alongside the proposed battery storage footprint, construction areas and retained land. Obtain the approved application, terms and conditions, plans and record drawings, and check the physical layout with the City and a qualified surveyor or engineer.

Woodland generally limits a service approval to the use area, facilities and proposed use described in the application. A connection or meter cannot serve property or a portion of property that the City engineer has not approved for it. Ask the City to confirm how the proposed boundaries affect the existing approval before assuming either side will retain service.

Illustration of a land parcel and surrounding landscape

A partial sale can trigger a signing deadline

Woodland Municipal Code section 13.44.030 requires a new site owner after a complete or partial change of property ownership to sign the recycled water operations, use and service terms within 30 days of the effective date of transfer or close of escrow, whichever is earlier. If the new owner does not sign within 30 days, the code calls for termination of recycled water service to the property on the 31st day following the change in ownership.

Identify the signing party and obtain the current terms before closing. If the property is subdivided, section 13.44.100 says the existing connection and meter thereafter serve only the lot or parcel on which the meter is located; additional mains, service lines, connections and/or meters are to be installed for additional new lots or parcels under the chapter. Confirm the required layout, approvals, cost and schedule with Woodland before committing to a closing date.

A lease still needs a service review

A lease may leave title and irrigation with the landowner, but a fence or construction access can still affect lines serving retained landscaping. Woodland defines a site owner to include a lessee under a lease of property served by City recycled water. Describe the actual lease and operation to the City and ask who must sign terms, hold service and supervise the system; do not assume the sale deadline applies to every lease.

In either a sale or lease, ask counsel to address access, protection, repairs, costs and responsibilities for retained lines, including during construction and after a project assignment. A private agreement does not replace City approval for service or system changes.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Separate a supervisor change from a system or use change

Each customer must designate a site supervisor subject to the engineer’s approval, keep the Director informed of the supervisor’s identity and ensure the supervisor attends City training at least once every five years. Arrange the handoff of operating records and contacts with the City when responsibilities change.

The code requires prior written engineer approval before a customer changes the recycled water system or facilities on property subject to service. Uses must be limited to those in the site owner’s engineer-approved terms and conditions and those approved for the service area. Discuss any proposed change to the irrigated area or use with the City before construction; a supervisor designation alone does not approve it. The City operates and maintains off-site facilities through the meter, while the customer maintains the service connection and on-site facilities.

Prepare for a land offer review

Share the property location, approximate acreage and proposed transaction with Sunland. Provide detailed plans privately if requested. Sunland reviews land sales, leases and existing agreement assignments for energy projects throughout the United States.

Ask the prospective developer for an exhibit showing equipment, fencing, roads and construction limits. Take that exhibit and the recycled water records to Woodland for a site-specific review before finalizing the transaction.

Questions landowners ask

Does a partial sale matter for Woodland recycled water service?

Yes. The code requires a new site owner following a complete or partial ownership change to sign the terms within 30 days of the transfer effective date or close of escrow, whichever is earlier, and specifies termination on the 31st day following the ownership change if the terms are not signed.

Can the existing meter serve both lots after subdivision?

Section 13.44.100 says the existing connection and meter thereafter serve only the lot or parcel where the meter is located. Ask the City about facilities and approvals for any additional lots.

Does a new site supervisor approve a changed irrigation area?

No. The supervisor designation is subject to engineer approval; separately, the City must approve applicable system changes and the permitted use and service area.

Sources & further reading

Sources checked 2026-11-17. Local rules and program details can change. Check the requirements for the actual project.