Alabama Code §37-4-22.1 defines a large-load data center customer using an executed retail electric service contract with expected total peak demand of at least 150 megawatts at one or more contiguous parcels. The facility must also meet Alabama’s statutory definition of a data processing center and operate solely for data processing. Ask Alabama Power which procedure applies to the contract for your site.
Under the Commission’s final order in Docket 33709, Alabama Power files a public petition naming the customer and its parent entities, the facility’s municipality or county, and the maximum contracted electric capacity. The contract and supporting documents go separately to the Commission’s Legal Division and the Attorney General. Ask the customer for authorized confirmation of the exact parcels, any phasing and the relationship between the named utility customer and the buyer or tenant signing your agreement.

Check the applicable review and the Commission’s decision
Start with the filing date of the petition for the contract at issue. Ask whether the petition was withdrawn or replaced and request the Commission disposition or written status from Alabama Power. The 90-day provision applies to petitions under the adopted large-load procedure. Ask the utility which process applied if the contract was handled during the transition from the interim review rules.
The Commission’s November 3, 2026 order approved the large-load rate with an amendment and directed Alabama Power to file the amended tariff with a November 23, 2026 effective date. Use the operative filing and confirmation for your contract when checking how the transition applies.
Compare the utility contract dates with your land agreement
Where an electric service contract would become void without Commission approval by a stated date, the final procedures say Alabama Power should submit its petition and accompanying documents at least 120 days before that date. Ask the project team to identify the actual contract date and show the petition filing and the land agreement’s option, payment or closing deadlines on the same calendar.
If your sale or lease condition calls for a written Commission order, ask counsel what evidence would satisfy it if the petition is deemed approved. Review any extension, notice or termination provisions in the actual land agreement. Ask Alabama Power and the project team separately what utility work, easements or approvals still affect when service can start.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss a data center property or existing agreement
Sunland welcomes inquiries from owners and authorized representatives across the United States about sales, leases and assignments of existing project agreements. Sunland may place property under contract and assign that agreement to a specialist developer. Share the general location, proposed transaction and next decision date. Arrange private follow-up for agreements and sensitive utility records you are authorized to share.
Questions landowners ask
What starts the 90-day review window?
Under the final Docket 33709 procedure, the window runs from the applicable petition filing. Ask the Commission or utility to confirm the date and current disposition for your contract.
What does the 120-day guidance refer to?
It refers to the time before the electric service contract would become void for lack of Commission approval. The land agreement governs its own deadlines.
Can the public petition identify the exact parcels and power delivery date?
Request confirmation of the parcel and phase from the customer and utility. The required public summary identifies the municipality or county and maximum contracted capacity. Ask separately for the conditions and schedule for service.
Sources & further reading
Sources checked November 22, 2026. Ask the Commission and Alabama Power which procedure and filing apply to the service contract for your project. Local rules and program details can change. Check the requirements for the actual project.