Reconstruct the service area
Gather prior site plans, plumbing and septic drawings, building permits, tenant information, environmental reports and any waste handling or closure records. Mark former bays, drains, sinks, tanks, pits and known underground lines on a plan along with the proposed equipment pads, trenches, access and staging areas. Note missing information rather than treating a blank plan as proof that nothing is present.
EPA cautions that plans may not reflect actual construction or later renovations. Its guidance suggests that a local health department or plumber using dye or smoke tests may help determine where a drain goes. Have a qualified professional select a safe investigation approach and coordinate access; do not open or disturb a suspected system yourself.

Determine where wastewater went
EPA describes a motor vehicle waste disposal well as a shallow disposal system receiving fluids from vehicle repair or maintenance. A service-bay drain connected to a septic system or dry well can be an example. EPA distinguishes drains connected to municipal sewer or to a holding tank whose waste is disposed of off site from this well rule, although other requirements can apply.
A suspected drain is a lead for investigation, not a regulatory classification. Ask the environmental professional and the responsible UIC authority to assess the actual facility, its use and destination, including any state requirements. If records are missing, ask what additional investigation and documentation are appropriate.
Check records before planning work
Ask the UIC permitting authority whether it has an inventory, permit, notice or closure record for the suspected system and whether more information or action is needed. EPA identifies several circumstances in which motor vehicle waste disposal wells are banned, including a nationwide ban on new motor vehicle waste disposal wells; location and state rules also matter. Do not assume a historical system was properly closed because the building was removed.
If closure is required, EPA says to contact the permitting authority before closing and describes advance written notification and approved closure to protect groundwater. The authority may impose additional requirements. An environmental professional and counsel can help assess records, potential investigation, reporting and responsibility under applicable law.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landUse the findings in a proposal
Provide the developer with the known location, mapped uncertainties and available records. Ask whether the layout can avoid suspected features during diligence, who may investigate, who pays, how access is controlled and how a finding affects deadlines or the transaction. Keep sensitive reports private until needed for review.
An owner or authorized representative in any state can ask Sunland to review a potential sale or lease; a party with an existing project agreement can also submit it for review. Share the site location, approximate acreage, your relationship to the property and the known former use. Ask counsel to review the actual agreement, including investigation rights and any assignment terms.
Questions landowners ask
Does every service-bay drain mean there is an injection well?
No. The destination and use matter. A qualified professional can help trace the system, and the UIC authority can assess applicable requirements.
Is a removed building proof the system was closed?
No. Ask for closure records and have missing information evaluated before excavation or a final layout.
Can the site still be offered for battery storage?
You can submit it for screening. The site history and any needed investigation or agency action are specific to the property and proposal.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.