Landowner guide

What happens to a BIA right-of-way when a battery storage project is sold?

A battery storage sale may include an existing road or electrical crossing over Tribal or individually owned Indian land. If the crossing uses a Bureau of Indian Affairs (BIA) right-of-way grant, confirm whether the deal assigns that grant and which records the parties must deliver.

The short answer

Read the original grant and amendments alongside the sale documents. If the grant will be assigned, check separately for required landowner consent and BIA approval. Section 169.207 also provides for assignments when the original grant expressly permits assignment without BIA approval, and for assignments that result from specified corporate transactions or operation of law. Those routes have recording requirements. Confirm which route applies with the BIA or Tribal realty office and counsel before relying on the crossing at closing.

Identify what the buyer will receive

Get the issued right-of-way grant, amendments, prior assignments and tract descriptions. Identify who holds the grant, its authority, what activities it authorizes and its remaining term. Compare those records with the land, equipment and agreements being sold. If a utility or the current project company will stay the grantee, confirm what rights the buyer needs to use or maintain the crossing under the grant and related agreements.

Give counsel the grant’s date and authority. Under section 169.7, for a grant issued before April 21, 2016, an explicit grant provision or the authorizing statute takes priority if it conflicts with a current procedural rule. Ask about older grants and applications that were pending when the rule changed before using the current assignment process.

Illustration of a land parcel and surrounding landscape

Check landowner consent and BIA approval separately

Under section 169.207(a), the grantee must satisfy the applicable landowner consent requirements in section 169.107 unless the grant expressly allows assignment without further consent. Tribal land and individually owned Indian land have different consent rules. Ask the appropriate realty office to confirm the land status, whose consent is required for the transaction and what evidence will establish it.

The grantee must also obtain BIA approval unless the assignment qualifies under section 169.207(b) or (c). When approval is required, section 169.208 gives BIA 30 days from receipt of the signed assignment, proof of required consents and other required documents to issue its written determination. If closing depends on approval, request that decision and resolve who supplies any required insurance, bonding or assumption documents.

Identify the documents due when BIA approval is unnecessary

Under section 169.207(b), the original grant must expressly allow assignment without BIA approval. The existing grantee and the assignee must provide the assignment and supporting documents to BIA within 30 days of assignment for recording in its Land Titles and Records Office (LTRO). Check landowner consent separately even when the original grant dispenses with BIA approval.

Section 169.207(c) separately addresses assignments resulting from a corporate merger, acquisition or transfer by operation of law. It still requires the assignment and supporting documents to go to BIA for LTRO recording within 30 days and to the Tribe for Tribal land. If the proposed sale changes who owns a company but leaves the grantee in place, ask counsel and BIA whether there is an assignment at all. Confirm the applicability of this provision to the actual transaction.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Put the crossing documents on the closing list

Agree on who obtains any required consents and approval, who sends the assignment package and when each party will receive a copy. Confirm with the relevant office what evidence it can provide of submission and recording. Keep that evidence, any required Tribal delivery and the signed grant with the closing documents.

If the buyer also proposes to change the route, authorized use or other grant terms, ask what additional review applies before committing the land or connection. Check separately which private access agreements or easements the buyer needs to use the whole route.

Discuss your property or existing agreement

Sunland welcomes inquiries from owners and authorized representatives nationwide about selling or leasing battery storage property or assigning an existing agreement. Share the general property location, your role and the transaction you are considering. Keep grant documents, trust ownership records and detailed maps private until there is an appropriate way to share them.

Questions landowners ask

Does permission to skip BIA approval also dispense with landowner consent?

Check the grant and the regulation for each requirement separately. Under section 169.207(a), landowner consent is required under section 169.107 unless the grant expressly provides otherwise, subject to the distinct rule in section 169.207(c).

When does the 30-day submission period apply?

For an assignment under section 169.207(b), the grantee and assignee send the assignment and supporting documents to BIA within 30 days of assignment for LTRO recording. Section 169.207(c) retains a 30-day BIA recording submission requirement and calls for delivery to the Tribe for Tribal land.

Should the parties review a grant issued before April 21, 2016?

Yes. Section 169.7 addresses earlier grants. Have counsel and BIA check the grant and its authorizing statute for explicit provisions that differ from the current procedural rules.

Sources & further reading

Current federal regulation and BIA guidance checked November 21, 2026. The process depends on the actual grant and transaction. Local rules and program details can change. Check the requirements for the actual project.