Map each tract and the full work area
Request a dated alignment showing parcel and tract boundaries, the proposed line and connection point, and any poles, equipment, trench, construction workspace, access roads, staging and restoration areas. Ask the developer to identify who controls each segment, including temporary work areas. A route drawn across a road or existing utility corridor does not establish that it has rights for the new line.
With the relevant realty office, confirm the legal descriptions, land status and recorded interests for every affected tract. Tribal trust or restricted land, individually owned Indian trust or restricted land, and fee land can require different permissions. A reservation boundary or map label alone does not establish the status of a specific tract. Request available title and existing right-of-way documents and have counsel check the actual records.

Check the existing grant before relying on it
Obtain the existing grant, map, amendments and any assignment or other relevant documents. Compare their holder, location, width, purpose, term and conditions with the proposed cable, construction and ongoing access. Ask the grant holder, BIA and counsel whether the existing authorization covers the proposed use and user, or whether a new or amended right-of-way or other approval is needed. Do not assume a road, distribution line or older utility grant authorizes a separate solar collector line.
Ask the developer who will secure rights on any fee interests as well. Part 169 does not authorize BIA to grant rights across fee land or collect compensation for fee interests; those rights must be addressed with the fee owners. BIA does not condition its grant across Indian land on obtaining fee owners’ rights and excludes fee interests when calculating the required consent percentage. Mixed ownership requires a tract-specific review.
Separate survey access from construction rights
Under 25 CFR 169.101, an applicant needing access to Indian land to prepare an application, such as for a survey, must obtain Indian landowner consent, but BIA approval for that access is not required. The rule also identifies circumstances in which BIA may grant permission to access. Contact the realty office about the land and appropriate consent before entry; ask that the scope, timing and restoration for any survey be clear.
Survey permission is not a grant to build or operate the line. For a new crossing requiring a Part 169 right-of-way, the applicant submits a complete application to the BIA office with jurisdiction. Required information includes the affected tracts, purpose, duration and documentation; BIA review addresses applicable environmental and cultural resource requirements. Establish the required grant and other authorizations before construction, and check the grant’s actual terms before work.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landUnderstand the owner and agency roles
For Tribal land, section 169.107 requires Tribal consent in the form of a Tribal authorization and, if the Tribe requires it, a written agreement. For individually owned Indian land, the applicant must notify all individual Indian landowners and generally obtain written consent from owners of a majority interest in each affected tract. That is a majority of interests, not a headcount. The regulation provides limited exceptions and rules for authorized representatives and BIA consent; ask the realty office how the particular record is treated.
Consent is distinct from BIA’s grant. BIA reviews a complete package and can grant or deny it under the regulations. The Tribe may also have applicable laws or conditions, and a route may involve multiple tracts and owners. Engage the appropriate Tribal and BIA offices early; do not assume any consent or approval is guaranteed.
Limit the promise to what you can deliver
Have counsel compare the developer’s proposed representation or delivery obligation with the land and rights you actually control. Allocate who identifies owners, negotiates and pays for rights, prepares surveys and applications, obtains approvals, and bears the cost or delay of denial or conditions. Consider deadlines, notice, route changes, an alternative alignment and termination or adjustment if a crossing cannot be secured. An alternative route also needs its own rights and review.
The fee-land solar lease or option and an offsite Part 169 crossing are separate questions. A solar lease on Indian trust or restricted project land may instead involve Part 162 and different rules. If discussing your fee parcel with Sunland, identify the known route issue and share supporting records privately when requested; an inquiry does not authorize entry on another owner’s land.
Questions landowners ask
Can a survey consent authorize installation of the collector line?
No. Survey access to prepare an application is distinct from the rights and approvals needed to construct and operate a crossing. Confirm the scope of each authorization.
Does a majority of owners have to sign every crossing?
For individually owned Indian land, section 169.107 generally requires written consent from owners of a majority interest in each affected tract and notice to all individual owners. Limited exceptions and representation rules apply; the Tribal-land rule is different.
Does an existing utility right-of-way cover the new line?
Not necessarily. Review its holder, purpose, route, dimensions, term and conditions with the grant holder, BIA and counsel before relying on it.
Sources & further reading
BIA right-of-way guidance and 25 CFR Part 169 were checked November 16, 2026. Land status, existing grants, consent, special authorities and approvals require tract-specific review. Local rules and program details can change. Check the requirements for the actual project.