Landowner guide

Can a buried battery storage connection cross an LWCF-assisted park?

A battery storage developer may propose a buried interconnection line across a neighboring park. If the park received Land and Water Conservation Fund (LWCF) assistance, the protected area and its public outdoor recreation use need special review. A buried cable or a line on a drawing does not itself establish permission to cross.

The short answer

Ask the developer to compare a route that avoids the park and obtain a plan of the entire proposed crossing. Ask the park sponsor and state LWCF office for the approved boundary map and project records, and for review of the proposed work and rights. The state may need to consult the National Park Service (NPS); do not rely on the crossing until the responsible parties have documented the applicable decision and rights.

Locate the protected boundary and the work

Ask the park owner or project sponsor and state LWCF office for the approved 6(f)(3) boundary map and other project documentation. Compare those records with a survey, property lines and the developer’s proposed alignment. The protected area may extend beyond the specific facility paid for by the grant. The boundary map is not necessarily a survey; ask a surveyor and the responsible agencies to resolve an uncertain overlap.

Request a plan showing the cable, trench or boring pits, temporary access and staging, tree removal, restoration, any cabinets or other above-ground equipment, and future inspection and repair access. Ask how long recreation areas would be closed and whether present or planned recreation would be affected. Also obtain existing easements and amendments; their location and terms need review before anyone assumes they cover a new line.

Illustration of a land parcel and surrounding landscape

Ask the sponsor and state how the proposal will be reviewed

NPS’s 2026 State and Local Assistance Programs Manual, Chapter 8, says a state may allow underground utilities in an LWCF boundary area if the ground above the alignment can be and is restored to its prior condition for continued public outdoor recreation within 12 months after disturbance. Unless an easement already exists, the arrangement must be a license or other limited use agreement; an arrangement granting a property right such as an easement constitutes a conversion. A license is not automatic permission.

The manual directs states to consult NPS on underground infrastructure proposals involving either new or expanded capacity under a pre-existing easement or right-of-way, or a new right-of-way without a pre-existing alignment. It also calls for NPS consultation if recreation use is not restored within 12 months or installation causes permanent above-ground changes. Impacts to present or future outdoor recreation opportunities in the corridor or elsewhere in the protected area trigger a conversion under the manual.

Understand the conversion question

A conversion is a change from protected public outdoor recreation use. NPS explains that a conversion requires approval and substitution of other recreation property meeting applicable value, usefulness and location requirements. Approval is not assured. The sponsor and state should identify whether the proposed work or rights require a conversion review and what information and approvals are needed before work proceeds.

Ask the sponsor who can authorize access to the park, whether the state will consult NPS on this plan, and what written determination or agreement is needed. Ask the developer who will prepare the submission, pay for review and restoration, and handle future repairs or a route change. State and local rules, other land rights and utility requirements may also apply.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Compare alternatives before committing the parcel

Ask the developer to compare feasible routes avoiding the park, including their land rights, engineering, costs and timing. An alternative shown on a map still needs its own rights and review. Have your attorney review any option or lease and its exhibits, including who bears route and approval risk and what happens if the crossing is unavailable.

Sunland welcomes nationwide inquiries about land and existing project opportunities. Share the property location, your relationship to it, approximate acreage if known and the proposed park crossing. Provide maps and relevant documents privately if requested for review.

Questions landowners ask

Does a buried line automatically qualify for a park crossing?

No. The proposed rights, construction, restoration and effect on outdoor recreation must be reviewed. Ask the park sponsor and state LWCF office about the proposal and any NPS consultation.

Does an existing easement settle the question?

No. Review its actual terms and alignment. The 2026 manual directs states to consult NPS on new or expanded underground infrastructure under a pre-existing easement or right-of-way.

Does a small LWCF grant protect only the funded improvement?

Not necessarily. Ask for the approved boundary map and project records: protection can extend beyond the specific improvement funded by the grant.

Sources & further reading

Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.

Want to ask about your land?

Send the location and what you know about the property. You don’t need a project plan, and you are not committing to a lease or sale.

Tell us about your land
Ask about your landTell us about your land