How can a data center appraisal change your ground rent?

A data center ground lease can call for base rent and a variable amount tied to the appraised value of individual facilities. The signed Carson County, Texas, ground lease involving Texas Tech University System and Fermi SPE shows how one agreement ties that calculation to subtenant rent receipts and annual appraisals.

Could my land work?

Before signing, ask what payment starts the appraisal schedule, which buildings count and who can appraise them. Have your advisers check the formula for any appraisal cap, exceptions for new improvements and credit for base rent. Put the report and payment dates in the lease so you can verify the amount due for each building.

Identify the receipt that starts the appraisal schedule

The Carson County lease starts the appraisal-based rent period when the ground tenant receives its first full rent payment, excluding prepaid rent, from the first operating subtenant covered by the clause. For each facility, the formula applies in the appraisal year the ground tenant receives the first full rent payment from the subtenant operating there and in later years.

Ask for a schedule showing each building, who occupies it and which receipt qualifies. If the tenant expects to fill the site in phases, check how it will document the payment and applicable appraisal year for each building.

Illustration of a landowner reviewing property plans

Check who appraises each facility and when

The Carson County agreement requires a qualified appraisal firm to use nationally recognized standards and procedures for comparable data center projects. It names eligible firms and permits another nationally recognized firm reasonably acceptable to the landlord. Ask what the appraiser must value and how you will receive and review the report.

The lease calls for the first assessment after the appraisal-based rent period starts and before its six-month anniversary. Later assessments for applicable facilities are due in the sixth month of each appraisal year. The ground tenant must promptly send the landlord a copy after receiving each assessment.

Check the value cap and the credit for base rent

The lease applies different percentages to different bands of appraised value. After a facility’s first appraisal year, it caps annual increases in appraised value at 3% on a noncumulative, noncompounding basis. The cap excludes qualifying new capital improvements the ground tenant or a subtenant completes that year, provided the preceding appraisal omitted their value.

The formula reduces appraisal-based rent by the applicable base rent. Under the first-year schedule, the installment is due within 30 days after the ground tenant receives the initial assessment, with no second installment for that year. For later years, compare both installment dates and the base rent actually paid with the lease’s offset rules. Ask for a worksheet that shows the prior appraised value, eligible improvements, base rent and the amount due.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Discuss a ground lease with variable rent

Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, the interest you hold and the proposed rent structure. Keep signed agreements, appraisals and payment records for private follow-up.

Questions landowners ask

Does the first subtenant payment count every planned building?

The Carson County lease tests when the ground tenant receives the first full rent payment from the subtenant operating in each covered facility. Track that event separately for each one.

Does the 3% value cap cover new improvements?

The Carson County lease excludes the value of new capital improvements completed by the ground tenant or a subtenant during the applicable appraisal year if the preceding appraisal omitted their value.

How does base rent affect the amount due?

The Carson County formula reduces the amount based on appraised value by base rent. Check the signed installment provisions and the base rent ledger before relying on a payment estimate.

Sources & further reading

Sources checked November 20, 2026. Fermi’s quarterly filing reported no variable lease payments as of September 30, 2026. A later qualifying rent receipt, appraisal or appraisal-based payment was unavailable to verify. Local rules and program details can change. Check the requirements for the actual project.