Start with the property and the right providers
Collect the address or parcel IDs, boundary survey, existing site plan, utility bills and known water and sewer connection records. Mark existing easements, buildings and access routes. Ask the local jurisdiction which public water and sewer providers would review the property; they may be different organizations. A service-area map is a starting point, not confirmation that the proposed demand can be served.
Ask whether the providers have infrastructure records for the parcel, whether extensions or off-site rights may be needed, and who should make a development inquiry. Do not assume an existing meter or former industrial use establishes capacity for a different project. The current owner can supply property records; the applicant and its engineer must develop the proposed demand assumptions.

Ask the project team for a usable demand profile
Request the anticipated average and peak water demand for each proposed phase, the schedule for each phase, and the intended uses, including cooling and ordinary building needs. Ask the engineer to state assumptions and identify any fire-protection demand separately. If the cooling design is undecided, request a range and the alternatives being considered rather than inventing a fixed number.
For wastewater, ask for estimated average and peak discharge, timing, expected constituents and the proposed destination. Cooling water consumption and sewer discharge need not be equal. Ask the wastewater provider what information, discharge review, metering or pretreatment it requires. Provide the same assumptions to both providers and update them if the project changes.
Use Loudoun Water's process as an example
For a property within Loudoun Water's Virginia service area, its pre-design page directs users to an engineering inquiry or pre-design meeting for feasibility and site-development questions. Its engineering inquiry accepts a project location, parcel ID or address and can be used to request a map of existing utilities. Loudoun Water says that map shows nearby water, sewer and reclaimed pipes and pipe sizes, but does not provide pipe capacity or flows.
A useful inquiry would identify the parcel, attach an available site plan and ask how the applicant should obtain a site-specific review of its phased water and wastewater needs. This is a local example, not a national application process. If a project is already submitted to Loudoun Water, its pre-design guidance directs questions to the assigned plan reviewer.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landTurn a response into a decision
Ask each provider to identify what its written response covers: demand assumptions, connection points, any studies or upgrades, off-site easements, costs, expected schedule, conditions and the period for which the response is valid. Ask explicitly what, if anything, reserves capacity and which later approvals and agreements are required. A favorable preliminary discussion does not itself establish a reservation or construction approval.
Loudoun Water's permitting page lists documents that may be required for an approved project, including an estimated flow acknowledgement, a process wastewater metering agreement and a non-residential sanitary sewer service request. Requirements depend on the project. The wastewater program also explains that some customers' flows go to receiving treatment facilities with applicable local limits. Ask the provider which requirements apply to the proposed discharge.
Start a property discussion
Share the property's location, acreage, existing use and any known water or sewer service with Sunland. You can submit even if a project design or utility response is not yet available. Sunland reviews submissions and may follow up; it may contract for a property and assign the agreement to a specialist. An inquiry does not guarantee a project or utility service.
Questions landowners ask
Does a water main at the boundary prove service is available?
No. The provider must assess the proposed demand and connection, and identify any improvements and approvals. A pipe map does not establish capacity or reserve it.
What if no data center operator has provided a water estimate?
Share the parcel and existing service records for an initial discussion, but label demand unknown. A prospective operator or engineer should provide project-specific assumptions before a capacity determination.
Is sewer discharge the same as water supplied?
Not necessarily. Ask the project engineer for separate supply and discharge estimates and ask the wastewater provider about its review and discharge requirements.
Sources & further reading
Sources checked 2026-11-15. Local rules and program details can change. Check the requirements for the actual project.
- Loudoun Water: Pre-Design (engineering inquiry, map limits and pre-design meeting)
- Loudoun Water: Engineering Inquiry Form (location and map request)
- Loudoun Water: Permitting Your Approved Project (potential permitting documents)
- Loudoun Water: Commercial and Industrial Wastewater Program (receiving facilities and local limits)