Check when the services agreement ends
Read the current services agreement against the proposed sale documents. Identify whose assets or ownership interests are changing hands and ask counsel which provision governs the handoff. Put the effective termination date on the closing schedule if the sale triggers it.
The signed agreement lists a sale of all or substantially all the assets of Monarch SPV HoldCo LLC or its subsidiary, Monarch Data Operations, LLC, as an event that ends the agreement. Section 9.5 sets the duties that follow.

List the records, assignments and approvals
The outgoing partner must cooperate with both Monarch entities, Zone Frontier and any successor development manager and deliver the project records it holds. The partner must assign or make available to the Monarch entities the project contracts, permits and vendor arrangements it is party to, as assignability and third-party consents allow.
For each item, identify who holds it, who should receive it, who can share it and when it is due. For each contract or permit, record the current holder, the proposed recipient and any required consent, assumption or agency approval. Keep signed approvals with the handoff list and give pending items an owner and a due date. If you are the landowner asked for consent, have counsel compare the proposed assignment with your lease, option or easement. Confirm who will owe payments and receive notices on the effective date.
Set the support period and payment deadlines
The Monarch partner must make key staff reasonably available to the successor for 180 days after effective termination on a time-and-materials basis. The parties may agree to longer. Monarch SPV HoldCo can add 90 days by delivering written notice to the partner at least 30 days before the initial period ends.
Both Monarch entities owe undisputed accrued compensation within 30 days after effective termination. Earlier liabilities, including earned but unpaid compensation, survive. For your sale, have the parties confirm who approves and pays for new transition work and document any amounts earned before termination, including items the parties still dispute.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss a project sale or land agreement
Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, which interest may transfer and your next decision date. Keep signed agreements and deal records for private follow-up.
Questions landowners ask
Does delivering a copy of a permit complete the transfer?
Check the permit and issuing agency’s requirements for the proposed change. Record delivery of the copy and the date any required agency approval takes effect.
How can the successor prepare to use a support period?
Agree which people can answer outstanding questions, who schedules their time and who approves their charges. Put any extension notice deadline on the closing schedule.
Sources & further reading
Sources checked November 20, 2026. The example describes the signed Monarch agreement. The public exhibit redacts the development partner’s name. Public records reviewed identify the original joint venture and leave any later asset sale or transition under the agreement unverified. Local rules and program details can change. Check the requirements for the actual project.