Identify the applications and owner signatures
Ask the buyer to send the application and proposed owner authorization together. Check the parcel, applicant, agency, scope and requested signature date. Have counsel confirm who has authority to sign and what the signature authorizes. Keep copies of the documents you sign and ask the buyer for the versions it files.
In the Soperton agreement’s Exhibit B, the Treutlen County Development Authority agreed to execute legally permissible owner consents, application signatures, affidavits and access authorizations needed before closing within five business days after a reasonable request. Section 4.3 also limits certain documents to those reasonably acceptable to the seller that do not impose material unreimbursed liability or specified payment or service obligations. Set response times and signature limits that work for your own sale.

Assign the permit work and costs
The Soperton agreement puts the buyer in charge of preparing, filing and following up on applications. The buyer pays its consultants and application and permit fees. The seller agrees to provide available records, coordinate reasonably with public agencies and help answer questions about ownership or site control. The seller covers its internal staff time and other costs expressly assigned to it.
Name a contact for each side. Agree who will collect records, coordinate meetings and answer agency questions. Ask counsel to review any request that could create a payment obligation or add work beyond the agreed seller role.
Decide what progress the buyer needs before closing
Section 6.2 conditions the buyer’s duty to close on a written determination, made in its reasonable discretion, that the proposed use is legally and technically approvable and that agencies have accepted the initial applications, begun reviewing them or provided a commercially reasonable path for them. The agreement allows closing before all construction permits are issued unless the buyer elects otherwise in writing.
For your sale, list the written evidence the buyer wants before closing and who will obtain it. Specify which items require an issued permit, which can be met by a review milestone and what the buyer and seller will do if the evidence arrives late.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landSet the end of any post-closing assistance
If the Soperton purchase closes, Sections 4.2 through 4.4 continue for 18 months after closing or until the initial building and site-development permits are issued, whichever comes first. Agree which remaining tasks the former owner will handle, who signs as the current owner after the deed and what record shows the seller’s assistance has ended.
Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, the type of owner signature requested and the next decision date. Keep signed agreements and applications for private follow-up.
Questions landowners ask
Who should answer the agency’s technical questions?
Check the purchase agreement. In Soperton, the buyer and its consultants handle technical responses, while the seller agrees to assist with matters such as ownership and site control.
Does the seller have to help with permits after closing?
Check the clauses that survive closing, the work they require and their end date. The Soperton agreement gives specified cooperation obligations an outside date and an earlier permit milestone that can end them.
Sources & further reading
Sources checked November 20, 2026. The amended offering circular reported that the project company had yet to acquire the land. The example describes the signed purchase terms. Local rules and program details can change. Check the requirements for the actual project.