Battery storage / Landowner guide

Smaller battery projects and DG: a landowner’s guide

A smaller project connected to local power lines is different from a large transmission-connected facility or a backup battery for one building.

The short answer

DG is often used for projects connected to a local distribution system. For a landowner, the important questions are which project is proposed, where it would connect and what land it needs. The label alone does not establish footprint, incentives or approval.

Ask which use is being proposed

A battery can serve a building or connect directly to the utility system. A building battery may be intended to manage that customer’s electricity use. A standalone land project has a different purpose and needs its own connection and site review.

If someone asks to lease your land, ask whether they are proposing a standalone project or equipment tied to an existing building. That helps make later questions about the layout and connection more specific.

Reference: U.S. Department of Energy: energy storage

Concept relief map of the United States with nodes and lines representing an energy storage network.

Separate project size from land size

A smaller project may have a different footprint from a larger facility, but it still needs equipment space, vehicle access and room for applicable clearances and drainage. Do not assume it can fit into any unused corner.

Power and stored energy describe different things. Megawatts, or MW, describe power at a moment in time. Megawatt-hours, or MWh, describe an amount of energy. Neither is a land-area measurement. An owner can provide acreage without calculating either.

A local connection still needs investigation

Distribution lines were not all built for the same uses or loads. The proposed charging and discharging must be reviewed. A nearby pole or commercial electric service does not establish that a standalone project can connect.

Ask the developer which utility process applies and whether the project is at an early inquiry, application or completed-study stage. Those stages should not be presented as interchangeable.

Reference: NREL: review of storage interconnection

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Find out what an available-capacity number measures

If an offer includes a capacity figure, ask for the document, its date and the line being quoted. Is it room under a customer program’s cap, an estimate for a particular circuit or a study for the proposed battery? Those figures answer different questions. A larger number does not necessarily describe a better site.

For example, Mecklenburg Electric Cooperative’s sheet updated August 1, 2026 subtracts installed net-metering systems from program caps for different customer categories. It is a program calculation, not a study of battery charging and export at your parcel. The public figure does not reserve capacity for a landowner.

Have the team explain which category and connection arrangement it believes apply. If its figure comes from a program sheet, request the separate electrical review still needed. Keep that answer beside the option timetable so you know what remains unresolved while your land is reserved.

Reference: Mecklenburg Electric Cooperative: net-metering program-cap calculation, updated August 1, 2026

Record being discussedQuestion for the developer
Program-cap calculationDoes this program apply to this design and customer?
Circuit map or estimateWhat site-specific review remains?
Project study or responseWhich design, conditions and application does it cover?

If the proposal promises savings on an electric bill

Identify the account that would receive the savings. Is it yours, a tenant’s or a new account held by the project company? Ask whether the offer pays for land, sells you a power service or combines both. A tenant receiving lower bills would not, by itself, explain what the property owner is paid.

Mecklenburg Electric’s net-metering page describes renewable generation on the customer’s side of the meter. Its linked rider was filed in April 2020 and describes generation intended primarily to offset the customer’s electricity requirements. These are customer-generation resources, not a blanket eligibility rule for a standalone battery lease.

For an actual battery proposal, get the current utility response for its charging, export and account arrangement. If there is existing solar equipment, have the team explain whether adding storage changes the approved design or requires further review. Do not use an older solar tariff as the complete answer for a new battery.

Ask how the private offer works if usage falls, the tenant leaves or the claimed savings are lower than expected. Would your land payment change, would equipment remain and who would carry the account costs? Have those points explained in the proposed documents before granting account authority or property rights.

Reference: Mecklenburg Electric Cooperative: customer-side net-metering explanation · Mecklenburg Electric Cooperative: linked Schedule NEM-10, filed April 2020; customer-generation applicability

Check programs against the actual project

A state may support more than one storage use. A program for a home battery or an existing business may have different rules from one for a grid-connected project on land. Ask for the name and current requirements of the program being discussed.

Do not choose a land agreement based only on an expected incentive. Ask how the proposal works if funding, timing or eligibility differs from what the developer expects.

Describe your property without the jargon

You can say: “I own a commercial parcel with an open area beside the driveway,” or “I would consider a few acres beside the farm entrance.” Add the location, county and state. Include the utility name and acreage if known.

You do not need to decide whether your land is a DG site. Sunland can begin with the property information and may ask for maps or other details. A later project review determines which route, if any, could fit.

Questions landowners ask

Does DG mean the battery must supply my building?

Not necessarily. Ask whether the proposal serves a customer or connects directly to the distribution system.

Is DG automatically eligible for an incentive?

No. Each program has its own rules for the actual project and application.

Is this only for farms?

No. You can ask about commercial land and other parcels as well. Each site still needs its own review.

Does room under a net-metering cap show battery capacity at my property?

No. It describes the program calculation. Ask for the applicable connection route and review of the actual battery’s charging and export.

Are electricity savings the same as rent for my land?

Identify who receives each payment or bill benefit. Have the private offer explain the land payment separately and what happens if customer usage or tenants change.

Sources & further reading

Sources checked 2026-10-07. Local rules and program details can change. Check the requirements for the actual project.

Want to ask about your land?

Send the location and what you know about the property. You don’t need a project plan, and you are not committing to a lease or sale.

Tell us about your land
Ask about your landTell us about your land