Check the agency and which records it holds
Florida Statutes Section 288.075(2)(a) covers specified information about a private party’s plans, intentions or interests in locating, relocating or expanding business activities in Florida. The provision requires a written confidentiality request to a defined economic development agency before an economic incentive agreement is signed.
Ask who holds the record and which provision the agency applies to it. The statutory definition of economic development agency includes FloridaCommerce and qualifying county and municipal economic development bodies. Separate records, such as permit filings or proprietary business information, can require a different review.

Use the agency’s receipt date and check for earlier disclosure
Under Section 288.075(2)(a)1, the exemption runs for 12 months after the agency receives the written request or until the information is otherwise disclosed, whichever comes first. The party’s signing date and the agency’s receipt date can differ. Ask for confirmation of receipt and any recorded disclosure.
Florida’s July 2026 amendment excludes covered data center information from the provision that can extend confidentiality for other business plans. It uses the general data center definition in Section 373.203. The separate large-scale data center size test applies to other provisions, including water-use permitting.
Verify the timing before relying on it in a deal
Section 288.075 also addresses timing when a final project order is issued for a signed economic development agreement. It refers to 180 days after issuance, a date in the order or earlier disclosure, whichever comes first, subject to the applicable outer limit. Ask the agency or counsel to interpret the actual order and confirm the timeline for the records involved.
If a sale or lease depends on an incentive decision, public hearing or permit, identify the agency document that will establish that milestone and agree who will obtain it. Confirm the records process with each relevant agency, including what filings and notices it requires.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss a proposed sale, lease or existing agreement
Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, proposed transaction and next decision date. Arrange private follow-up for agreements and records you are authorized to share.
Questions landowners ask
When does the 12-month period start?
Section 288.075(2)(a)1 measures it from the economic development agency’s receipt of the written request. Earlier disclosure can end the exemption sooner.
Can the agency use the standard extension for covered data center plans?
The Florida amendment excludes covered information relating to data centers from that extension. Ask the agency to confirm the rule for the records involved.
Does the same exemption govern a data center’s permit filings?
Ask the permitting agency which disclosure and hearing rules apply. Section 288.075(2)(a) addresses specified economic development information held by a defined agency.
Sources & further reading
Sources checked November 22, 2026. The records amendment took effect July 1, 2026. This guide uses no project-specific request, agency decision, final project order or disclosure record. Local rules and program details can change. Check the requirements for the actual project.