Compare the buyer’s plan with the current permit
Confirm the permit holder, expiration date, approved use and allocation. Florida Statutes Section 373.239 allows a permittee to seek modification of an unexpired permit. Give the permitting agency the current authorization and proposed changes, and ask what applies to any change in ownership or permit holder.
St. Johns River Water Management District’s permitting materials list separate filing types for permit transfers and modifications. Ask the agency for your property to confirm which filing it needs and what written decision would cover the buyer’s proposal.

Check the two triggers for initial-application review
Under Section 373.239(2), the agency treats a modification in the same manner as an initial permit application under Section 373.229 if the proposed change involves water use of 100,000 gallons or more per day or if a large-scale data center proposes it. Either trigger is sufficient. Section 373.239(3) separately applies initial-application treatment to renewals.
Section 373.203 defines a large-scale data center using anticipated monthly peak load at a single location. It uses a threshold of 50 megawatts or more, measured by the highest average over a 15-minute interval. The definition includes qualifying colocation parties at one location and excludes aggregation across the same customer’s separate locations. Have counsel and the agency confirm whether the definition applies to the buyer’s proposal.
Put the hearing and filing requirements on the closing schedule
Under Section 373.262(4)(b), the water management district or department must hold a hearing before it approves a covered large-scale data center permit application. Subsection (4)(a) separately requires water-use accounting and a conservation plan when a large-scale data center application requests an allocation of at least 100,000 gallons per day in average daily flow.
Ask the permitting agency which filing and hearing milestones apply. Agree with the buyer who will prepare the application, provide updates and obtain the written decision. If your agreement depends on approval, identify what the decision must cover and how a delay affects closing.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss a property with an existing water-use permit
Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, proposed transaction and next decision date. Keep permits, plans and detailed water-use records for private follow-up.
Questions landowners ask
Can the large-scale data center trigger apply below 100,000 gallons per day?
Yes. Section 373.239(2) lists the water-use amount and a proposal by a statutory large-scale data center as alternative triggers.
When are water-use accounting and a conservation plan required?
Under Section 373.262(4)(a), a large-scale data center application needs those additional materials when it requests an allocation of at least 100,000 gallons per day in average daily flow.
What should I request before relying on an existing permit?
Get the current permit and amendments. Ask the permitting agency to confirm the permit holder, what the authorization covers and how to handle any proposed change or transfer.
Sources & further reading
Sources checked November 21, 2026. The cited Florida water-use provisions took effect July 1, 2026. This guide uses no project-specific permit, application, allocation or agency decision. Local rules and program details can change. Check the requirements for the actual project.
- Florida Laws Chapter 2026-65, Sections 4–6 and 8
- Florida Statutes Section 373.203, definitions
- Florida Statutes Section 373.239, modification and renewal
- Florida Statutes Section 373.262, large-scale data center permitting
- Florida Statutes Section 373.229, permit applications
- St. Johns River Water Management District, permitting materials