Confirm the County can review the phase
This guide covers capacity through Frederick County’s water and sewer systems. For municipal service, make the request to the municipality. Start with the address and tax map and parcel numbers. If the County provides only one of the services, ask the other provider separately about its records.
Frederick County’s September 14, 2026 executive order pauses review of covered applications until July 1, 2027 unless superseded or ended earlier. The order excludes applications for covered facilities on property that obtained an approved Adequate Public Facilities Ordinance Letter of Understanding before June 17, 2025. Give County Planning any approved letter and the proposed phase map. Ask whether a boundary change, new building or added phase can proceed before you promise a closing date.

Ask what the County has assigned to each parcel
Gather the allocation notice, water and sewer capacity fee receipts, approved plans, any tap agreement and amendments, and the proposed survey or plat. Use the County’s Engineering & Planning service inquiry to request a written response. Ask the Division to identify the parcel, the amount of water and sewer capacity assigned, the use it covers, the status of payment and connection, and any rescission or return of capacity.
Section 10 assigns allocations to the property, with commercial or industrial capacity based on the identified use. Additional capacity depends on the actual user’s construction plans. Section 16 limits service under a Water/Sewer Service Application to the building listed in it. If the buyer proposes a new building or buys only part of the property, ask the Division what capacity and service would cover that building or lot and what would remain available to the seller.
Check the dates and financial guarantees
Section 10.B, which addresses allocation when capacity is scarce, generally requires allocated capacity to be used within two years unless an effective Multi-Year Tap Agreement sets the terms. The County Executive may rescind unused commercial or industrial capacity after that period. Ask which deadlines apply to your allocation, what the County counts as use, and whether any amounts have been rescinded. A minimum service charge can begin one year after payment of the capacity fee if the property remains unconnected under that provision.
A Multi-Year Tap Agreement needs County Executive approval. Read the approved agreement and current tap schedule. Under Section 10.B.5, the owner has 30 days from official written notice of allocation to purchase the first calendar year’s capacity. Missing that deadline may void the agreement or lead the County to draw on an existing guarantee. The rules also address secured Public Works or Public Improvements Agreements when capacity is allocated as part of establishing or expanding a treatment system. Ask for the payment and guarantee records that apply to this property.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landMatch the utility evidence to the proposed closings
Put the current parcel and each proposed lot on the same map. For each phase, record the acreage, proposed use and building, capacity the Division confirms, next fee or guarantee, use deadline, and proposed closing date. If a buyer’s second closing falls beyond the confirmed use deadline, ask who will obtain and pay for an approved change and what will happen if the County declines it.
Have the purchase documents identify which party pays each fee or posts each guarantee before closing, which written County confirmations are needed, and how an existing seller guarantee will be released or replaced. Address later-phase deposits, extension rights and retained land separately if the buyer wants to close on the first lot while keeping an option on the rest. You can contact Sunland with the location, approximate acreage and the phase decision you face.
Questions landowners ask
Can a buyer use the parent parcel’s allocation on the first lot it buys?
Ask the Division to confirm assignment and service for the proposed lot and building, along with the balance for retained land. The existing allocation record identifies the capacity assigned to the current property.
What if two years have already passed?
Ask the Division whether the use deadline applies, whether any unused capacity was rescinded, and whether an approved Multi-Year Tap Agreement governs the allocation. Obtain its status in writing before relying on it.
Does payment of a capacity fee settle which phase can proceed?
Check the payment record alongside the allocation, approved use, applicable development approvals and tap schedule. Ask County Planning which phases can proceed and which require additional review.
Sources & further reading
Sources checked 2026-11-19. Local rules and program details can change. Check the requirements for the actual project.