Confirm which applications and permits cover the work
Ask the developer which agency is reviewing the project and whether it needs a construction or alteration permit under Fla. Stat. §373.413. Get the application, any issued permit and the approved drawings and conditions. Ask the permitting office which version and conditions apply to the proposed clearing or grading.
Section 163.3205 excludes sites that were the subject of a solar construction application submitted to a local government before July 1, 2021. If the developer refers to an older application, ask for the dated filing and a map of the site it covered. Confirm with the relevant agencies how the statute applies to the proposed work.

Check the construction plan and inspection arrangements
For solar construction requiring permits under §373.413, §163.3205(5)(a) requires site-specific protections in the erosion and sediment control plan. These include onsite soil percolation testing, runoff and erosion controls based on rainfall amounts up to the site’s 100-year, 24-hour design storm, and phased clearing and stabilization as needed. Ask the project team to point out the test locations, runoff controls and clearing sequence on the drawings.
The law requires inspections during construction by a certified Florida Stormwater, Erosion, and Sedimentation Control Inspector. The operator must implement the construction and operational permit requirements developed and applicable under §163.3205(5)(a). Ask who arranges inspections, how issues get fixed and when you will receive inspection and correction records under the agreement.
Check the separate rule for permanent drainage in Northwest Florida
For new solar facility applications filed after July 1, 2026, §163.3205(5)(b) applies to an operating-phase stormwater management system permitted under chapter 373, part IV, within the Northwest Florida Water Management District. It requires design based on the project site’s 100-year, 24-hour design storm. Ask the permitting office to confirm the district boundary, actual application date and design requirements for the system.
Compare the approved operating plan with the lease exhibit. For example, if a basin outlet is near acreage you intend to farm, ask the project engineer to show the drainage path and who will have access for maintenance. Review with counsel who pays for maintenance, how changes to drainage or access are approved, and what the agreement requires if water affects retained land.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDescribe the work when you inquire
Sunland welcomes nationwide inquiries from landowners and authorized representatives about solar land sales, leases and assignments of existing agreements. Share the general location, your role and whether clearing or drainage work has been proposed. Keep signed agreements, detailed plans and permit records for private review.
Questions landowners ask
Which drawings should I ask for before clearing?
Ask for the current permit and approved erosion and sediment control plan, with the areas to be disturbed, the clearing and stabilization sequence, and runoff controls marked. Compare those drawings with the site access described in your agreement.
Does the July 2026 application date apply to construction inspections?
The application-date cutoff in §163.3205(5)(b) applies to the separate operating-system design rule in the Northwest Florida Water Management District. The construction plan and inspection requirements are in §163.3205(5)(a) for solar construction requiring permits under §373.413.
What should I ask about land outside the solar fence?
Trace drainage lines, outlets and maintenance access on the plans. If any affect land you intend to keep using, ask the project team and your counsel how the permit and agreement address that area.
Sources & further reading
Florida’s current statutes, Chapter 2026-2 and Northwest Florida Water Management District permit guidance were checked November 21, 2026. The basin outlet example is hypothetical. Confirm the permit history, applicable requirements and approved plans for the specific project. Local rules and program details can change. Check the requirements for the actual project.