Georgia landowner guide

What happens to irrigation when a Georgia solar parcel includes the surface-water intake?

A proposed solar sale or lease can place a creek or river intake and pump on the project parcel while the fields they irrigate stay with the farm. A working pump and an existing permit do not by themselves resolve who can enter the solar site, run the equipment or deliver water after the transaction.

Could my land work?

Map the intake, pump, meter, power supply and lines through to each retained field. Obtain the current agricultural withdrawal permit and contact the Georgia Environmental Protection Division (EPD) about the proposed ownership, operator and field changes. Have counsel provide durable access and utility rights in the sale or lease documents before the split takes effect.

Trace the water system across the proposed boundary

On a survey or site plan, mark the stream, intake, pump, meter, electrical service, controls, buried and aboveground pipes, crossings, gates and irrigated fields. Include the route for people and equipment to reach the intake during construction and operations. Identify landowners and existing easements along the entire route, including any land outside the proposed solar parcel. Locate the system on the developer’s layout for panels, fencing, roads, grading and cable trenches.

Gather the permit and amendments, pump and meter information, withdrawal and irrigation records, deeds, leases and recorded easements. Compare the permitted withdrawal location, capacity, use and acreage with what is actually operating and the planned retained fields. An agricultural permit and physical access are separate questions: neither a project map nor historic use alone establishes all the rights needed after a sale or lease.

Illustration of a land parcel and surrounding landscape

Discuss the proposed arrangement with EPD

Georgia EPD says an agricultural water withdrawal permit is needed for a person withdrawing more than 100,000 gallons per day; for surface-water systems it describes the threshold as pumping in excess of that amount on a monthly average. Smaller withdrawals may still raise other rights or regulatory questions. Ask EPD to confirm the permit’s current status, terms and metering obligations and how they apply to this particular intake and planned operation.

Explain who will own the land and equipment, who will hold the permit and operate the pump, and which fields will receive water. Under O.C.G.A. section 12-5-31(b)(3)(C), a permittee may apply to transfer or assign a farm-use surface-water permit to subsequent owners of the subject lands; EPD must receive written notice. Changes to the permitted use or capacity conditions or to the subject lands require an application for the director’s review and approval. Withdrawal under a revised permit may begin on the effective date stated on it. Ask EPD how these rules apply to a split ownership. EPD provides an application to transfer ownership or modify an agricultural withdrawal permit. Ask whether a transfer, modification, both or another action is needed, what supporting maps and signatures are required, and when the revised arrangement can operate. Do not assume the land transaction automatically transfers or changes the permit. Submit a separate agricultural withdrawal application for a new or existing unpermitted withdrawal as EPD directs.

Keep continuing irrigation distinct from inactivation

If the retained fields will continue to be irrigated, discuss the continuing operation with EPD rather than treating inactivation as the transfer procedure. EPD’s inactivation notification is a voluntary request to make the agricultural permit inactive for possible future use; the form states that future use requires 60 days’ written notification to EPD. It also asks whether surface-water pumps are permanently out of service. Confirm the implications for the specific permit with EPD before signing or stopping use.

Local basin restrictions matter. In the 2012 Flint River Basin Suspension Area, EPD describes specific eligibility rules for existing surface-water withdrawals and modifications, including historical cutoff dates and potential volumetric conversion for certain changes. Surface-water withdrawals generally are not eligible for drought-restricted permits, subject to the off-stream well-to-pond exception EPD describes. A new or larger intake, changed acreage or pump capacity should be checked with EPD early; approval is not assured.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Protect access, utilities and the intended use

Have Georgia counsel document the rights needed across the solar parcel for inspection, operation, emergency repair and replacement of the intake, pump, meter, power and pipes, including access routes, gate and security procedures, utility easements, notice and scheduling. Address costs, electricity, maintenance, outages, relocation, damage, restoration, insurance and access during construction. In a sale, consider recorded rights that bind successors; in a lease, coordinate reserved rights with the lease and any lender or assignee interests. Confirm rights from any third-party landowner and utility provider separately.

Ask the developer to identify any proposed project water demand, such as construction or panel washing, its source and quantity. Do not assume an agricultural irrigation permit authorizes that separate nonagricultural use: ask EPD which requirements apply and arrange an approved supply before use. This guide concerns surface-water irrigation; a well or groundwater source has different permitting and construction questions. Sunland welcomes solar land sale, lease, assignment and existing project or agreement inquiries from owners and authorized representatives nationwide. Share the location and acreage, and provide permit and layout documents privately if requested.

Questions landowners ask

Does a solar sale automatically transfer the agricultural permit?

Do not assume it does. Ask EPD whether transfer, modification or another action is needed for the proposed owner, operator and irrigated fields, and arrange the necessary land and utility rights separately.

Should I inactivate the permit if the retained fields will still be irrigated?

Discuss continuing irrigation with EPD first. Its inactivation form is for voluntarily making a permit inactive for possible future use, with written notice required before future use.

Can the solar project use irrigation water for construction or washing?

Do not assume the farm-use permit covers that use. Identify the proposed source and demand and ask EPD about the applicable requirements.

Sources & further reading

Sources checked 2026-11-17. Local rules and program details can change. Check the requirements for the actual project.

Want to ask about your land?

Send the location and what you know about the property. You don’t need a project plan, and you are not committing to a lease or sale.

Tell us about your land
Have land in Georgia?Tell us about your land