Virginia · Data centers
Can a data center fit on your Henry County, Virginia, land?
Sources checked
Check the layout and both county decisions
Henry County’s August 25, 2026 amendment created a Data Center (D-C) District without rezoning any land. For land outside that district, a developer pursuing a data center under the amendment needs a parcel rezoning to D-C from the Board of Supervisors. Once the land is zoned D-C, the developer needs a separate special use permit from the Board of Zoning Appeals for the proposed development. Before giving a developer control of your land, check whether the proposed buildings and equipment fit the required setbacks and what the option requires at each decision.
If a developer asks to option your Henry County land for a data center, ask for a drawing with the zoning of every adjoining tract. The same parcel can have a 500-foot setback along one side and a 1,000-foot setback along the other.
Check the zoning along each property line
Start with the county parcel map and a current survey. Ask Planning, Zoning and Inspections to confirm your parcel’s zoning and the zoning on each adjoining tract. The county’s map page directs readers to verify zoning with staff. Along a street frontage, mark the 100-foot setback from the street right-of-way. For all structures, mark a 500-foot side or rear yard beside industrially zoned land and a 1,000-foot yard beside land in other zoning classifications. Ask staff how to draw the setbacks where adjoining zoning changes along the same boundary.
Suppose your tract is 1,750 feet wide between parallel side boundaries, with industrial zoning along one side and agricultural zoning along the other. In this example, the two side yards leave 250 feet across the middle. A proposed 400-foot-wide building cannot fit that strip. Ask for a revised drawing that also shows the front and rear setbacks, equipment, entrances and any easements. If the developer proposes adding land to make the building fit, identify the specific tract and ask the county how the new project boundary would affect the setback calculation before changing the option.
Sources August 25 Board minutes, Article XX Data Center District and §§ 21-2100–2101 · Adopted §§ 21-2003–2004, front setback and side and rear yards · Henry County parcel maps and zoning verification
Track the rezoning and special use permit separately
The county’s rezoning process calls for a public hearing before the Planning Commission, which makes a recommendation, and a separate hearing before the Board of Supervisors, which decides the zoning change. The Board of Zoning Appeals holds its own hearing on the special use permit and can attach conditions to the project. Start with the case numbers and compare the parcel descriptions and drawings across both records.
| Record to request | What to check for your land |
|---|---|
| Planning Commission recommendation | Confirm the parcel IDs, recommended action and next Board of Supervisors hearing. |
| Board of Supervisors rezoning decision | Verify the D-C classification and the exact land covered. Ask for the final map and any terms of the approval. |
| Board of Zoning Appeals special use permit | Check the approved use, site plan, conditions and the land covered. Compare them with the footprint, entrances and equipment shown on the option exhibit. |
Sources August 25 Board minutes, vote adopting the data center zoning amendment · August 25 Board minutes, Article XX Data Center District and §§ 21-2100–2101 · Henry County rezoning application and decision form · Henry County special use permit application and hearing process
Ask what still stands between rezoning and a permit decision
The data center permit application must document site control or the right to use the site as proposed. The general rezoning form also calls for the owner’s consent when the owner and applicant differ. Before signing either an option or a consent, have your attorney compare the land and rights described in each document with the current plan.
Ask the developer for the status of the third-party water supply impact study, the electrical infrastructure analysis and utility documentation of adequate existing capacity. County staff must receive and review the water study before the county accepts the application as complete. The ordinance calls for closed-loop cooling. The application also calls for a third-party acoustical analysis and written Virginia Department of Transportation confirmation for the entrances.
Sources Henry County rezoning application and decision form · Adopted § 21-2102, data center special use permit application · Adopted § 21-2103, site and operating standards · Henry County Department of Planning, Zoning and Inspections
Set the option acreage and extension terms from the plan
If the project also depends on an adjoining parcel, ask whether the developer could proceed with a smaller first phase if that parcel is delayed. Use that answer to discuss whether the option should release the unused land on a separate date.
- Compare the survey, verified adjoining zoning and dated layout with the proposed option exhibit. Mark the land, access routes and utility corridors the developer wants to hold.
- If the developer wants more time after rezoning, decide with your attorney which record would justify an extension. Examples include a complete permit application or the Board of Zoning Appeals’ written decision.
- Agree when the developer releases acreage and corridors it no longer needs. Ask for an updated exhibit if a permit condition moves an entrance or equipment.
Sources Adopted §§ 21-2003–2004, front setback and side and rear yards · Adopted § 21-2102, data center special use permit application · Henry County special use permit application and hearing process
Common questions
Does existing industrial zoning let my buyer build a data center?
Under the adopted amendment, data centers require a special use permit in the D-C district. Ask county staff to verify the parcel’s current classification and whether the buyer has either decision for its proposal.
Does Henry County set a minimum parcel acreage for the D-C district?
Article XX sets no minimum area. The front, side and rear yard requirements still apply, so check the dimensions and adjoining zoning before deciding how much land the project needs.
Which document confirms the county approved the layout for this use?
Ask for the Board of Zoning Appeals’ special use permit, its conditions and the plan it covers. Check the county’s parcel rezoning decision separately and compare both records with the plan attached to your land agreement.
Sources
- August 25 Board minutes, Article XX Data Center District and §§ 21-2100–2101
- August 25 Board minutes, vote adopting the data center zoning amendment
- Adopted §§ 21-2003–2004, front setback and side and rear yards
- Adopted § 21-2102, data center special use permit application
- Adopted § 21-2103, site and operating standards
- Henry County rezoning application and decision form
- Henry County special use permit application and hearing process
- Henry County parcel maps and zoning verification
- Henry County Department of Planning, Zoning and Inspections