Virginia landowner guide

Which homes and schools should a Virginia data center’s sound assessment cover?

If a buyer proposes a new large data center on part of your Virginia property, ask for the boundary shown in its local siting application. For covered projects, Virginia requires the applicant’s assessment to examine sound at homes and schools within 500 feet of the facility’s property boundary, to the extent practicable. Compare that boundary with the land you would sell, lease or keep.

Could my land work?

Ask the planning office which application the developer filed and whether the project meets the state’s 100-megawatt threshold for expected retail utility power. Get the dated boundary map and any submitted sound assessment. If your house or a nearby school is within 500 feet of that boundary, ask how the assessment considers it and whether a later layout changes the review.

Check the local application and expected utility load

Virginia Code §15.2-2209.5 uses the term high energy use facility for a project that, when the applicant files for rezoning, a special exception or a special use permit, is reasonably expected to need at least 100 megawatts of electrical power from the utility providing retail service. Ask the applicant for its filing and expected utility load, then confirm with the local planning office which process applies.

Before approving one of those applications to site a new covered facility, the locality must require the applicant to perform and submit the sound assessment within the applicable statutory review timeline. If the proposal expands or modifies an existing or approved facility, give the planning office the prior approval and proposed load increase so it can determine how the statute applies.

Illustration of a land parcel and surrounding landscape

Map the uses near the proposed facility boundary

Request the dated boundary exhibit and the assessment’s map of residential units and schools. Use the facility property boundary identified for the application when you compare the map with your option or lease exhibit. A sale of part of a tract can leave a home on retained land near that boundary. Ask the planning office which boundary it uses if the application shows several parcels or phases.

Check which version of the layout the applicant assessed. If equipment, parcel lines or phases move, ask whether the assessment needs an update and request the current version. The 500-foot distance describes the state assessment area. Ask which local setbacks, noise standards and zoning conditions apply to the site.

Ask what the locality received and what it decided

The law also directs the locality to require a form from the serving utility before approving a covered siting application. The form describes substations expected to serve the facility and anticipated transmission voltage, to the extent known and practicable. Ask for the status of that filing, the actual siting decision and any conditions. Confirm the status of power service, easements and access separately.

The locality uses the submitted information to assess consistency with its plans and compliance with applicable requirements. It may also ask for an assessment of specified resources, such as water or farmland on or immediately next to the site. Ask the planning office which materials it needs and who can confirm that the current layout was reviewed.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Use the reviewed layout in the sale, lease or option

If the review changes the boundary or facility layout, compare the revised acreage, access and retained uses with the land agreement. Have counsel identify which exhibit controls, who pays for a new assessment and which local decision or condition must be documented before the next notice, extension or closing deadline.

Sunland welcomes data center sale, lease and existing agreement inquiries from owners and authorized representatives nationwide. Sunland may place property under contract and assign the agreement to a specialist developer. Share the general location, proposed transaction and decision date, and arrange private follow-up for detailed maps and agreements.

Questions landowners ask

Where does the 500 feet start?

Section 15.2-2209.5(B) uses the high energy use facility’s property boundary. Ask the locality for the boundary used in the application and how it treats nearby residences or schools in the review.

Does the state rule specify a 500-foot setback?

The distance determines which homes and schools the assessment examines to the extent practicable. Ask the locality for its applicable setbacks, sound standards and zoning conditions.

Who submits the assessment and the utility form?

The applicant submits the site assessment. The utility providing retail service submits the form on substations and anticipated transmission voltage, to the extent known and practicable.

Sources & further reading

Sources checked November 22, 2026. Ask the local planning office to confirm which application, boundary exhibit and current layout it is reviewing. Local rules and program details can change. Check the requirements for the actual project.