Who reviews a solar farm that crosses township lines in Ingham County?

Sources checked

Start with the full project map

Ask the developer for the total solar capacity, a dated map and the local case numbers or state docket. Michigan’s Public Act 233 applies to solar facilities rated at 50 megawatts or more and allows state review in specified circumstances. Your township clerk can help you find the plans on file for your parcel. If there is a state case, check the latest order and its referenced drawings before agreeing to a lease or easement.

A developer may want your field in one township and an entrance or cable route in another. Before you sign, find out which offices have the proposal and whether the latest public plan shows the same land and access rights as the agreement in front of you.

Find every jurisdiction the proposed facility touches

Start with the parcel number on your tax bill. Ingham County Equalization and Tax Mapping links to parcel maps and local assessors. Use those records to identify the township and compare the mapped parcel with your survey or deed. Ask the developer for an overall plan that labels municipal lines and the parcel numbers for proposed panels, equipment, entrances and cable routes. Mark the specific areas the developer wants to use on your land, including any temporary work area.

Under Michigan’s siting law, a facility can occupy multiple parcels, even parcels that do not touch, when they share a point of interconnection. The 50-megawatt threshold applies to the solar facility’s nameplate capacity. Ask for the whole project’s rating and how your acreage fits into it. The Court of Appeals held that affected local units include jurisdictions where the facility is proposed, including counties, even when a jurisdiction lacks zoning authority. Ask the developer which offices received the plan and which have authority to act on this project.

Sources Ingham County Equalization and Tax Mapping · Michigan Public Act 233, §§ 221–224, 226 and 230 · Michigan Court of Appeals, No. 373259, May 7, 2026 opinion as amended

Find out where the developer has applied

Ask each relevant township clerk for the latest meeting notice, site plan and any application or written decision. If the developer expects a state certificate, ask for the Michigan Public Service Commission case number and look up the case in the state’s current siting applications. Michigan law calls for a copy of the site plan to go to each affected local clerk when that plan is submitted to the Commission.

Under § 223(3), timely notice from the chief elected officials that each affected local unit has a compatible renewable energy ordinance can require local applications. Under the statute, a compatible ordinance allows energy facilities under requirements no more restrictive than § 226(8). Ask for the ordinances and written notices that the developer is relying on. Where a local application has been filed under § 223(3), the statute generally gives the local unit 120 days from receipt to act, with up to 120 more days by agreement. A missed decision deadline, denial of an application that meets § 226(8), or a qualifying ordinance change can allow a state filing. A local government exercising zoning jurisdiction may also ask the Commission to require a state certificate.

What the developer tells youWhat to ask for
“We’re still talking to the townships.”Current plan, list of affected local units, meeting dates and any written ordinance notices.
“We filed with the township.”Application receipt date, case number, documents filed there, any agreed extension and the written decision if issued.
“The state has approved it.”Commission docket number, certificate order, applicable conditions and the dated plan named in the order.

Sources Michigan Public Act 233, §§ 221–224, 226 and 230 · Michigan Public Service Commission, current siting applications

See how the Acceleration Solar records fit together

The public notice filed with Vevay Township in 2025 shows how one proposal reached several offices. It described the same 90-megawatt project in Leslie, Onondaga and Vevay townships and listed an Onondaga meeting and a joint Leslie–Vevay meeting. The Commission’s order recounts an initial June 18, 2025 filing that was deemed incomplete and a revised application filed October 3, 2025. The Commission says the affected local units did not each have a compatible ordinance, so the case came before the state. The three townships took part in the state case, and Ingham County reached a separate host agreement.

On August 27, 2026, the Commission approved the settlement in docket U-21932. Ordering paragraphs C through E and Exhibit A § III.F point to the filed application and specify how the plans may change, including the changes listed in Attachment A. If someone shows you the original public-meeting map, ask for the approved revision, the settlement attachments and any later approved change. Compare the sheet and revision date before relying on the acreage or access shown. Use the same check for a different project with its own case number.

Sources Vevay Township, Acceleration Solar public meeting notice · Michigan Public Service Commission, August 27, 2026 order and settlement in U-21932 · Michigan Public Service Commission, Acceleration Solar settlement summary · Michigan Public Service Commission, docket U-21932

Check the dates if the filing route is disputed

Ask the developer and the relevant clerk when the developer offered to meet with the chief elected official, when that meeting took place, and when the official gave notice of a compatible ordinance. The Court of Appeals held that the statute’s 30-day ordinance-notice period runs from the meeting itself. On November 20, 2026, the Michigan Supreme Court directed argument on whether to hear cross-appeals involving the notice deadline, including what should happen if a meeting never occurs or is unreasonably delayed. The order placed the matter on the January 2027 calendar.

If a developer says a missed deadline switched your project to state review, ask for the dated correspondence and the current record supporting that route. Have your attorney check any disputed deadline before you authorize a filing or agree to dates for possession.

Sources Michigan Court of Appeals, No. 373259, May 7, 2026 opinion as amended · Michigan Supreme Court, No. 170249, November 20, 2026 order

Compare the approved or proposed plan with your agreement

Suppose the latest plans move a road out of one township and put the entrance on the field you intend to keep farming. Ask for a marked-up drawing showing both routes, temporary work limits and the gate you still need. Confirm with the reviewing office whether the changed plan is on file and whether it calls for further review. Then compare the drawing with the legal description and each access or cable easement in the proposed agreement.

Ask your attorney what the option, lease and easements allow before and after approval, who must consent to a route change and how any unused strip will be released. Section 230(4) excludes eminent domain authority from the powers conveyed by a PA 233 certificate. Ask to see the signed agreement or easement that gives the project the specific rights it says it holds.

Sources Michigan Public Act 233, §§ 221–224, 226 and 230 · Michigan Public Service Commission, Acceleration Solar settlement summary

Common questions

Where do I find a solar site plan if my township is only part of the project?

Start with your township clerk and ask for the latest plan and its revision date. If there is a Commission case, check the docket for the plan filed there and any later order or amendment.

Does a township or county host agreement give the project rights over my land?

Ask for the private instrument that covers the exact land at issue, such as a signed access agreement, easement or lease. The host agreement in the Acceleration Solar case was between the developer and the local government.

Do the Acceleration Solar plans tell me what is allowed on my parcel?

Use docket U-21932 to check the plans and conditions for that particular project. For a different proposal, ask for its own case number, the decision if one exists and the plan that shows your parcel.

Sources