Check where the easement clause reaches
The signed August 2022 Cline ground lease for Wood Duck Solar in Barren County, Kentucky, illustrates how the two boundaries can differ. Section 6 excludes the area shown on Exhibit B-1 and labeled Do Not Disturb Area from the defined land. Section 28(a)(iv) expressly includes that area in a separate exclusive easement provision that lists underground power and communication lines, battery storage equipment and related facilities. Section 28 limits those easements to rights reasonably required in connection with the lease and its intended use.
Read the definitions, exhibit boundaries and every grant that can reach the area you want to keep. Check both construction and long-term use. A route you expected to allow for an underground cable may be described in terms that also cover access, maintenance or equipment. Ask the developer to show each proposed use on the same plan so you can decide what to accept.

Choose between a full exclusion and a limited crossing
If the area must stay free of project activity, ask counsel to carry that limit through the land description, grant language and all related exhibits. Check clauses for temporary work, staging, emergency access and relocation, as well as the permanent equipment areas. Name the activities and boundaries precisely enough for the parties to use the same plan in the field.
If you can accept a specific use, have the project team show the corridor, the portion needed for temporary work and the areas your use depends on. For example, if you will allow a cable across a retained field, decide whether the agreement permits a surface cabinet, a widened work area or future entry to replace the cable. Put any separate compensation, maintenance and restoration terms into the written agreement.
Agree on the final area before signing the easement documents
In the Cline lease, section 28(b) calls for good-faith negotiation and mutual agreement on the final adjacent land subject to the easements. It also calls for the landlord to deliver documents reasonably requested by the tenant, in recordable form, within 20 days of its written request. Have counsel review how an approval step and a delivery deadline work together in your own agreement.
Keep the final survey, signed approval and any recorded instrument with the lease. Have counsel and title compare the final grant with what you agreed to keep. The public Wood Duck records reviewed show the signed lease terms and a conditional certificate for the solar facility and transmission line. They leave any final Cline easement instrument and battery installation unverified.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss the area you want to retain
Sunland reviews battery storage land sale, lease and existing agreement inquiries, including potential assignments, across the United States. Share the property location and describe the area you want to keep and any proposed crossing. Keep the signed documents, exhibits and survey available for private review.
Questions landowners ask
Is excluding an area from the lease enough to keep it undisturbed?
Compare the exclusion with each easement and temporary access clause. Have the signed documents state the limits for every right that could reach the retained area.
Can I agree to a cable crossing while keeping the rest of the field?
Identify the exact corridor and what work may occur there. Agree on any temporary access, repair and restoration duties, and how changes will be approved.
What should I check before signing the easement itself?
Compare the final survey, legal description and grant with the lease and written approvals. Ask counsel what must be signed or recorded and which time limits apply.
Sources & further reading
Sources checked November 20, 2026. The Cline lease illustrates one signed contract. The reviewed public records leave later private amendments, the final footprint of any easement and battery installation unverified. Local rules and program details can change. Check the requirements for the actual project.