Virginia landowner guide

What did Compass Creek annexation change for data center land?

A buyer near Compass Creek may use a Leesburg address or point to utility work at the nearby Microsoft campus. Before you set a closing date, check whether the land entered the Town, which service agreement covers the proposed phase and who controls any existing development guarantees.

Could my land work?

Start with the court-approved annexation plat and your parcel survey. Compare the buyer’s proposed phase with the provider agreements for that land, then ask the Town and County for the current holder and release terms of each outstanding performance agreement or guarantee. If the buyer needs a boundary change, a provider commitment or a written release, give each item its own deadline and proof in the sale contract.

Put the buyer’s acreage on the court-approved plat

A November 2024 order approved the annexation of about 401 acres at Compass Creek, effective January 1, 2025. The recorded order, instrument 20241127-0051419, includes a survey plat and a legal description. Section 4.2 of the settlement required written consent before a property could be included. Compare the recorded boundary with the parcel IDs and the survey for both the buyer’s acreage and any land you plan to keep.

If the buyer needs acreage outside the existing Town limits to join Leesburg, ask both jurisdictions which process would apply. Section 8.2 preserves the option of a voluntary boundary adjustment under specified conditions, including the landowner’s contemporaneous written consent. It also states that the Town and County may accept or reject a proposed adjustment. Ask the buyer to show the land it wants included and what happens to your sale if either jurisdiction declines.

Illustration of a landowner reviewing property plans

Read the service agreements for the exact phase

Section 5.1 calls for Leesburg to serve the annexed area under its usual Town policies. Section 5.2 contains a separate provision for development or redevelopment on the Microsoft property after the IAD05 data center. The provision calls for a request from the property owner and a commitment from Loudoun Water before Leesburg must facilitate that service. Section 5.3 preserves the Town’s discretion over utility capacity and service decisions.

Leesburg’s utility project page describes a March 2024 customer service agreement covering additional water and sewer availability for Microsoft’s IAD-01 through IAD-05 campus. Utility project 25506 includes a new waterline connection at Sycolin Road. If a buyer presents an existing service agreement for your land, ask the provider to confirm in writing the parcel, facilities and phase it covers, whether the buyer needs an assignment or a new agreement, and which infrastructure costs and construction milestones affect service.

Find out who can release the existing guarantees

On July 15, 2026, Loudoun County’s Board of Supervisors approved conveyances to Leesburg of County interests in easements, performance agreements and related financial guarantees for land development in the annexed area. The vote authorized the County Administrator to execute the conveyance instruments. County staff identified examples such as stormwater, emergency access and utility easements and explained that the related guarantees generally secure construction tied to those rights.

For the land you would sell or retain, list each affected easement and performance agreement by recording or file number. Ask the Town and County for the executed instrument and current status. For any open guarantee, confirm who holds it, what work it secures, who provided it and who can issue a written release or accept a replacement. If the buyer proposes to assume an obligation, ask whether the current holder will also release the seller and any seller-provided security.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Tie the sale dates to documents you can verify

Have the purchase agreement identify which boundary decision, provider commitment, easement instrument or release must be in hand for each closing. If the buyer needs an easement across land you will keep, mark the permanent route and temporary work area on the survey. Address access during construction, restoration and who pays if the utility route changes.

If a buyer wants more time to obtain a provider commitment or a release, ask for a specific extension date and the document that will show progress. For a property discussion with Sunland, share the acreage, parcel IDs and the boundary, service or guarantee decision affecting your sale. Sunland also considers land sales, leases and existing project agreements nationwide.

Questions landowners ask

Can adjoining acreage use the Microsoft provision for Loudoun Water service?

Section 5.2 applies to qualifying future development or redevelopment on the Microsoft property. Ask the providers for a written determination for the land and phase in your offer.

Which document shows whether my parcel was annexed?

Start with the recorded final order and its survey and legal description. Ask Town or County staff to compare those exhibits with your current parcel survey, especially if the property was split or renumbered.

Does the County’s conveyance vote release my development guarantee?

The vote authorized conveyances of County interests. Ask the Town and County for the instrument covering your guarantee and written confirmation of who can release or replace it.

Sources & further reading

Sources checked 2026-11-19. Local rules and program details can change. Check the requirements for the actual project.