Check the boundary and current zoning for each parcel
Use the Linn County land records and rural zoning maps to check the parcel IDs, current zoning and city limits. Ask County Planning & Zoning to confirm the district for unincorporated land. For land within a city, contact that city’s zoning office. If a proposal spans both, ask each office to confirm which parcels it reviews.
Section 107-151(d) in the County’s February 2026 ordinance calls for a major site plan for a large-scale data center and a rezone to EU-3 if the land is outside that district. Ask staff which rules apply to the full proposal. Section 107-180 uses the combined power and water figures for all buildings on a phased or multi-building campus when determining its scale.

Find out which application the buyer needs
The Board of Supervisors adopted the pause on July 1, 2026. It is scheduled to end at 11:59 p.m. Central Time on January 1, 2028. The Board can extend it or end it early under the resolution. Ask County staff whether a new EU-3 rezone is required and when they expect to accept the filing for review.
If the buyer points to an earlier application, ask for the file number, filing date and parcels listed, then check its status with the zoning office. If the land already has EU-3 zoning, ask staff which site plan and permit steps still apply. Put the filing, acceptance for review and any required rezoning decision on your schedule as separate events.
Compare County milestones with the option deadlines
Put the option expiration, extension notice and fee deadlines beside the dates the buyer can substantiate. If the option calls for filing an application or obtaining a zoning decision, agree what document will show that milestone was met. A hearing schedule may still be uncertain when a filing becomes possible.
Before granting more time, have counsel review who can extend the option, any payment due for an extension and what happens if a filing or decision is delayed. If the buyer seeks more time without a confirmed filing date, decide how long the land can remain under option and what will happen to any option payments if the deadline passes.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss a sale, lease or existing agreement
Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, the approval step and your next decision date. Keep signed options and private documents for follow-up.
Questions landowners ask
Does the Linn County pause apply to land inside a city?
The County describes the EU-3 pause as applying to unincorporated land. If your parcel is inside city limits, ask that city’s zoning office which rules and filing schedule apply.
What can I verify if a buyer says it already filed?
Ask for the application file number and filing date. Confirm with the zoning office when the application was accepted, which land it covers and its current status.
Sources & further reading
Sources checked November 20, 2026. Linn County confirms adoption of both measures and posts unsigned copies of the approved texts. Check the County’s current status before relying on the scheduled end date. Local rules and program details can change. Check the requirements for the actual project.