Maine landowner guide

Does the sale of an older Maine solar project trigger a decommissioning plan?

Before consenting to a transfer of an older Maine solar project on your land, ask who will own and operate it after closing and whether the state has approved a decommissioning plan. A change in the legal entity that owns or operates the project can bring an older site with at least three acres of ground-mounted panels under Maine’s solar decommissioning law.

Could my land work?

Get the original construction start date, a plan showing the acreage the panels occupy, and the legal names of the current and proposed project owners and operators. Ask the Maine Department of Environmental Protection or the Land Use Planning Commission whether the deal triggers a first plan or requires approval to transfer an existing one. Request the written decision and evidence of financial assurance before agreeing to a lease consent or release.

Check the construction date and the panel acreage

Maine’s solar decommissioning chapter applies to developments with ground-mounted panels occupying three or more acres where construction began on or after October 1, 2021. It also applies to developments with that panel acreage that undergo a covered transfer on or after that date. A project built before the cutoff may therefore need its first state-approved plan when it changes hands.

Ask the project company for a dated construction record, the current site plan and the acreage used for the panel threshold. Ask the permitting agency how it measures that acreage if the plan gives only the total leased or fenced area. Check the project’s transfer history too. An earlier covered transfer may have already brought the project under the chapter.

Illustration of a land parcel and surrounding landscape

Compare the legal entities before and after closing

Maine defines transfer of ownership for this chapter by a change in the legal entity that owns or operates the solar development. A stock or membership-interest sale or exchange, or a merger, falls outside that definition when the legal entity that owns or operates the project stays the same. Ask for the before-and-after legal names and a brief description of what the transaction transfers.

If you are selling the underlying land or signing a lease assignment, confirm whether the deal also changes the project owner or operator. Have counsel compare the transaction documents with your signed lease to see whether a consent, notice or assignment is required under the contract.

Ask which plan approval the project needs

Maine requires approval of a decommissioning plan before operating a covered project. Ask the responsible agency whether it already has a plan on file and, if this transaction brings the project under the chapter for the first time, what the project parties must obtain to keep operating after the change.

If the project already has a plan approved under the chapter, the law keeps the transferor jointly and severally liable for carrying it out until the permitting agency approves the plan transfer to the new owner or operator. Ask for the dated approval that identifies the successor.

The Maine Department of Environmental Protection handles projects located wholly or partly outside the unorganized and deorganized areas, as well as projects subject to its jurisdiction under the Site Location of Development Law. The Land Use Planning Commission handles projects wholly within those areas that fall outside that DEP jurisdiction. Give the agency the project location and existing permit number when you ask who has the file.

What the project records showWhat to ask for
Earlier construction and an upcoming change in the project owner or operatorThe agency’s determination on applicability and, if required, the first approved plan.
An existing approved plan and a covered project transferThe agency’s approval transferring the plan to the named new owner or operator.
The same project owner and operator after a change in investor ownershipThe records showing which legal entities stay in place and any notices or consents your lease requires.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Match the state documents to the lease you are being asked to sign

For plan approval, Maine requires the responsible party named in the plan to demonstrate financial assurance for the full cost of decommissioning. Ask for the current bond, irrevocable letter of credit or other agency-accepted instrument. Check the named party, the covered work and the agency’s acceptance against the current plan and any proposed assignment.

Have counsel review the scope and timing of any consent or release. Compare the state records with your lease’s removal, restoration, rent and guaranty terms, and write down which approvals and documents the project parties should provide before your signature takes effect.

Sunland accepts nationwide inquiries from landowners and authorized representatives about solar land sales, leases and assignments of existing agreements. Share the general location, your role and the proposed transfer or deadline. Keep signed agreements and financial assurance documents for private review.

Questions landowners ask

Can an older Maine solar project need its first decommissioning plan after a sale?

Yes. A project with ground-mounted panels occupying at least three acres comes under the chapter if it undergoes a covered transfer on or after October 1, 2021. A covered project needs an approved plan to operate.

Does a sale of membership interests trigger the law for an older project?

A sale or exchange of membership interests falls outside the chapter’s transfer definition when the legal entity that owns or operates the development stays the same. Check the exact legal entities and your lease separately.

What if the project already has a Maine-approved plan?

Ask for written agency approval of the plan transfer to the new owner or operator. For a covered transfer of a project with an approved plan, Maine keeps the transferor jointly and severally liable for implementation until that approval.

Sources & further reading

Maine statutes and the Department of Environmental Protection’s solar decommissioning page were checked November 22, 2026. Confirm your project’s construction history, panel acreage, ownership and agency file. Local rules and program details can change. Check the requirements for the actual project.

Want to ask about your land?

Send the location and what you know about the property. You don’t need a project plan, and you are not committing to a lease or sale.

Tell us about your land
Have land in Maine?Tell us about your land