Map the work beyond the solar fence
For a new ground-mounted project, Maine’s statute and Chapter 575 look at developments of five acres or more that occupy high-value agricultural land (HVAL). The rule’s HVAL definition includes a one-contiguous-acre threshold and can combine qualifying prime farmland and farmland of statewide importance. Keep the development acreage and the acreage of qualifying soils on separate lines in the developer’s work map.
Ask the developer to show the full project area as defined by Chapter 575. It can include new roads, buried utilities and rights of way, vegetation clearing, equipment laydown and temporary access. Some existing conditions, such as paved surfaces or areas already stripped of topsoil, can be excluded under the rule. Have the developer identify the basis for any exclusion it uses.
Suppose the fence avoids a field but a new road and a temporary equipment area extend into it. Ask for the disturbed areas and soil boundaries on one exhibit, then compare a layout that moves the road or staging. Ask DACF whether each version changes the acreage considered or the permit needed.

Ask what the field survey actually covered
DACF’s September 2026 identification protocol treats aerial images and existing soil maps as screening tools. To confirm the presence of soil-based HVAL, the soils inventory must be done in the field by a licensed Maine soil scientist. The field-based survey also considers current and past site uses and inventories structures and hard surfaces. A single survey component can be enough to exclude land under the rule when it disqualifies the area.
Request the survey scope, date, soil boundaries and findings, and check them against the latest layout. Ask whether proposed access, utility and temporary areas were checked and how any exclusion was documented. Chapter 575 provides specific treatment for blueberry barrens, PFAS-impacted land and certain individual permit applicants that elect compensation on the entire project land area. Ask DACF which evidence applies if the developer is relying on one of those provisions.
| Decision | Records to ask for |
|---|---|
| Allow limited survey access | Survey scope, agreed entry routes and dates, people allowed on site and terms for any damage. |
| Accept a layout for the deal | Dated plan for all permanent and temporary work, survey map and findings, and documented DACF feedback on that layout. |
| Allow clearing or construction | Applicable permits and conditions, evidence that any required preconstruction conditions are satisfied, and the final exhibit attached to the agreement. |
Tie early access to the work you intend to allow
Chapter 575 counts activities such as vegetation clearing, grading, excavation and installation of equipment as construction start. Have counsel review what the option or other access agreement authorizes now. Identify the specific survey activities, entry routes, notice and repair terms, and ask DACF about proposed testing or fieldwork if there is any uncertainty about when work may begin.
Have counsel review how the agreement handles a survey that finds qualifying acreage or a later request to shift a road, cable or staging area. Identify who pays for surveys and redesign, who can agree to a changed exhibit, and whether the option, possession or start date can move while the permit question is resolved.
Request copies of any required approvals and conditions before construction. Chapter 575 treats its permit as provisional until the applicant has obtained the other required approvals and satisfied any applicable compensation requirement. Ask the developer to show that the permitted footprint matches the work it plans to start.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss a solar land opportunity
Sunland welcomes inquiries from landowners and authorized representatives across the United States about sales, leases and assignments of existing solar agreements. Share the general location and the upcoming access or agreement decision. Keep signed agreements, maps and survey results for private review.
Questions landowners ask
Is the online soil map enough to confirm high-value agricultural land?
Use it for an initial screen. DACF requires field verification by a licensed soil scientist to confirm qualifying prime farmland or farmland of statewide importance for this program.
Can a temporary laydown area matter if it is outside the fence?
Yes. Chapter 575 includes temporary impacts in its project land-area definition. Ask the developer to show the laydown area and confirm that the survey and permit review cover the applicable footprint.
What if the developer moves a road after the survey?
Compare the revised route with the survey boundary. Ask DACF whether the change needs more survey work or a permit revision before the developer uses the route.
Sources & further reading
Maine law, the adopted rule and DACF guidance were checked November 21, 2026. Ask DACF to confirm the applicable process for the current project layout and proposed start date. Local rules and program details can change. Check the requirements for the actual project.