Massachusetts landowner guide

Can a public owner use Article 97 land for battery storage?

A municipality or other public custodian may receive a battery storage proposal for a parcel, access strip or utility corridor held for conservation or recreation. If the affected land or interest is protected by Article 97, the owner must evaluate alternatives and the statutory replacement process as well as legislative authorization before promising the rights needed for the project.

Could my land work?

First have counsel confirm Article 97 status and identify the public entity with care and control. Map the complete proposed rights and work, compare feasible alternatives, and identify potential replacement land and costs with the Executive Office of Energy and Environmental Affairs (EEA). A public owner’s willingness to negotiate, or an EEA submission, does not itself authorize a change in use or disposition.

Identify the protected interest and the proposal

Collect the deed, taking or acquisition documents, purpose of acquisition, custodial orders, prior votes, restrictions and any grant agreements. Ask counsel whether the particular public land, easement or other interest is subject to Article 97 and who has care and control. A municipal map, vacant appearance or conservation label alone does not resolve that question; Article 97 can apply without federal park funding.

Obtain a drawing and draft instrument showing the battery pad, fence, access, cables, staging, grading, construction and maintenance areas, duration and rights over retained land. A sale, easement, lease, transfer of control or change of use may require review. EEA guidance describes a limited revocable permit or license as outside this disposition process only when it transfers no land interest and authorizes no change in use. Its label alone is not decisive.

Illustration of a land parcel and surrounding landscape

Compare alternatives before committing

Massachusetts General Laws chapter 3, section 5A requires public and EEA notice and an alternatives analysis demonstrating that options to avoid or minimize the disposition or change in use were explored and no feasible or substantially equivalent alternative exists. The analysis must be submitted to EEA and made public. Identify the public purpose and document alternatives rather than relying on a general statement that the project is beneficial.

Compare available sites and routes outside protected land, including reasonably obtainable private property where appropriate, and assess smaller footprints or different construction methods. Explain why each alternative is or is not feasible or substantially equivalent and how remaining impacts would be minimized. EEA guidance says cost should not be the dispositive factor for dismissing alternatives. Retain the maps, engineering, availability and cost evidence supporting the comparison.

Find and protect qualifying replacement land

Ordinarily section 5A calls for replacement land or an interest not already subject to Article 97, in a comparable location, with equal or greater acreage, natural resource value and monetary value. EEA determines natural resource equivalency. The public entity must take, acquire or dedicate the replacement in perpetuity for Article 97 purposes. The guidance also says replacement cannot already be otherwise protected in perpetuity.

Start with the lost land’s actual conservation or recreational purpose and use, not acreage alone. Review candidate ownership, legal description, existing restrictions, resource features and suitability for comparable use with EEA and the public custodian. A suitable parcel may require improvements to serve the same purpose. A parcel already publicly owned but not protected may be eligible; its actual status and the proposed perpetual dedication require review.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Appraise the affected and replacement interests

The statute measures monetary value using an appraisal of fair market value or value in use, whichever is greater. A narrow access corridor may have a modest standalone market value yet a higher value in use if its location enables a larger project. Do not budget replacement costs by multiplying square feet by an assumed vacant-land price.

Provide the appraiser with the actual rights, project context, surveys and any retained restrictions. EEA guidance discusses appraisal materials for both affected and replacement land and the public entity may have additional standards. Ask EEA and the owner what documentation is needed for the proposed legislation and subsequent acquisition, who commissions it, and who pays. Describe both areas precisely enough for the petition and eventual recorded instruments.

Understand limited waiver and funding routes

The Secretary of EEA may waive or modify the replacement-land requirement in specified circumstances, including a transfer of legal control between public entities with no other change, or a transfer of a parcel under 2,500 square feet with insignificant natural resource and recreation value that serves a significant public interest. Each statutory condition matters and the decision is discretionary. Size alone is not an automatic exception, and a change in use cannot be assumed to qualify as a control-only transfer.

Funding in lieu, or a combination of funding and land, is a conditional route rather than a fee anyone may elect to pay. It requires the Secretary’s reported findings, including significant public interest, no adverse impacts on an environmental justice population, the publicly noticed and commented alternatives analysis, and infeasibility of contemporaneously designating qualifying replacement. The Legislature must address the proposal; ask counsel and EEA about the specific submission and authorization.

Plan the in-lieu obligation and legislation

Where the in-lieu route is authorized, the statute requires funding of at least 110% of the affected land’s fair market value or value in use, whichever is greater, determined after an independent appraisal. Funds must be held in the applicable dedicated account and used within three years to acquire replacement land meeting the statutory location, acreage, resource and value standards and dedicated in perpetuity. Budget the acquisition and continuing obligation rather than treating the payment as the end of the process.

Article 97 requires a law enacted by a two-thirds recorded vote of each legislative branch for the covered change or disposition. Section 5A specifies materials accompanying the legislative petition, including the alternatives analysis, replacement description where applicable, appraisal and any waiver or required findings. A replacement waiver does not waive the constitutional legislative requirement. EEA review or tracker posting is not legislative approval or an endorsement by the public owner.

Coordinate authority, other restrictions and contract terms

Ask public counsel which local or agency approvals, notices and votes apply to the actual transaction and when they must occur. The guidance does not impose a universal rule that the alternatives analysis must precede every local vote; coordinate the applicable process and petition requirements with counsel and EEA. A private developer should work with the entity holding care and control and document its approval where needed.

Review deed restrictions, federal or state grant conditions and other applicable permits or environmental review separately. Article 97 legislation does not itself release an independent grant restriction. In a proposed agreement, address who prepares and pays for alternatives, appraisals, replacement acquisition, improvements and legal work; make the rights, closing and entry contingent on the actual required authorizations and documents. Provide for changed layouts, delays and failure to obtain approvals.

Discuss the site with Sunland

Sunland welcomes nationwide battery storage land sale, lease and existing agreement inquiries from owners and authorized representatives. A public custodian can share the location, approximate acreage, protected interest, proposed footprint and existing uses. A private proponent should coordinate with the public owner before representing that the site is available.

Sunland may contract for a property or agreement and then assign its interest to a specialist developer, subject to the actual terms and required consents. The public entity and its counsel should evaluate alternatives, replacement obligations, authority and the complete agreement before committing rights.

Questions landowners ask

Does a small battery access strip avoid Article 97?

Not automatically. A replacement waiver for a parcel under 2,500 square feet requires the other statutory conditions and a discretionary Secretary decision. It does not waive required legislative authorization.

Can the owner pay money instead of finding replacement land?

Only through the conditional statutory route and required authorization. The Secretary must report specified findings, and dedicated funds must be used to acquire qualifying replacement land within three years.

Does an EEA determination approve the battery project?

No. EEA’s determination under the process is separate from public-owner consent, legislative authorization and other applicable reviews and restrictions.

Can land already protected forever serve as replacement?

EEA guidance says replacement land cannot already be subject to Article 97 or otherwise protected in perpetuity. Review the actual interest and proposed dedication with EEA and counsel.

Sources & further reading

Massachusetts statute, constitution and currently linked EEA guidance checked November 18, 2026. No individual title, proposal, replacement parcel or approval was reviewed. Local rules and program details can change. Check the requirements for the actual project.