Verify how the local permit was issued
For a covered small clean energy infrastructure facility, constructive approval applies if the local government issues no final decision within the 12-month review period. Section 29.10 measures that period from receipt of a complete Consolidated Local Permit application or from the date the application is deemed complete. Under section 29.12, the Common Conditions apply to the resulting local permit.
Ask the local permitting representative for the constructive approval with the town clerk’s stamp, the application it covers, and any later modifications or review proceedings. Compare the facility, drawings and parcel with the property or rights being transferred. If the local government issued a decision on the application, read that decision and its transfer terms with your adviser.

Assign the notice and proof before closing
The transfer condition covers a change in ownership of the facility or the property, a change of leaseholder, and a change of the company operating the facility. Write down which changes are part of the closing and when each takes effect. Identify the permit applicant, the successor and the person responsible for providing each document.
The Common Conditions require the applicant to send the notice to the local government by U.S. Postal Service First-Class Mail within 30 days of the change. The applicant must also give the local government proof of the transfer to a successor. Ask what proof it expects for your transaction and agree who will supply it. Keep a copy of the notice and evidence of when it was mailed.
Plan the successor’s meeting
The successor is to meet with the local government within 30 days of the notice or at a mutually convenient time. The meeting covers pre-construction or ongoing construction activities, or operating conditions if the facility is in service. Agree before closing who will request the meeting and what records the successor needs to bring.
Ask the outgoing party for current plans, the compliance record and a list of deadlines or unfinished requirements. Identify who will supply missing documents or finish work after closing. Keep the meeting confirmation and any agreed follow-up with the permit file.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landReview what follows a facility sale
Under section 29.14, the sale of a permitted small clean energy infrastructure facility carries its permit conditions and requirements, mitigation obligations and any Community Benefits Agreements to successors in interest. Ask for the actual agreements, payment records and open commitments. Review them alongside the lease or deed and the terms that allocate costs and responsibilities between the parties.
A successor may ask the local government to modify existing permit obligations on an individual basis. The local government has discretion over whether to grant that request. If the price or closing date depends on a change, ask your adviser how the agreement should handle the time needed for a decision and what happens if the request is declined.
Discuss your property or existing agreement
Sunland welcomes inquiries from owners and authorized representatives nationwide about selling or leasing battery storage property or assigning an existing agreement. Share the general property location, your role and the transaction you are considering. Keep signed agreements, permit files and title records private until there is an appropriate way to share them.
Questions landowners ask
Can selling the land alone trigger notice under the Common Conditions?
Yes. On this constructive approval route, the transfer condition expressly includes a change in property ownership. Confirm the actual permit and identify the applicant responsible for filing.
Does the successor have 30 days from closing to meet with the local government?
The meeting period runs from the notice. The Common Conditions call for a meeting within 30 days of the notice or at a mutually convenient time.
Can a buyer change existing permit conditions after a facility sale?
Section 29.14 lets a successor petition the permitting authority for individual changes. Confirm the current requirements and account for them while the request is under review.
Sources & further reading
Massachusetts statute, published regulation and final Common Conditions checked November 21, 2026. Confirm the permit record for the property before applying the transfer condition. Local rules and program details can change. Check the requirements for the actual project.
- Massachusetts General Laws, chapter 25A, §21, consolidated small-facility permits
- Massachusetts Department of Energy Resources, 225 CMR 29.00, §§29.10, 29.12 and 29.14
- Massachusetts Department of Energy Resources, Guideline on Constructive Approval and Common Conditions
- Massachusetts Department of Energy Resources, current siting and permitting materials