Can a stalled solar project come back in Mecklenburg County, Virginia?
Sources checked
Check the current zoning and the last county decision
Mecklenburg County’s replacement zoning ordinance took effect July 1, 2026. It allows non-shared utility-scale solar in A-1 Agricultural and M-1 Industrial districts with a special exception permit. Before extending an option, give the Zoning Administrator your parcel numbers and the old application or permit number. Ask whether the proposed layout can be considered and what decision the developer still needs.
If a developer comes back to a Mecklenburg County property after an earlier proposal stalled, start by finding out whether the project was denied, withdrawn or approved. That record helps you decide whether to renew site control and how much time to give the developer.
Verify the current district for each parcel
For land in unincorporated Mecklenburg County, give the Zoning Administrator each tax parcel number, the old project name and a dated drawing of the new proposal. Ask for the district under the current zoning map. If a tract straddles a district line, ask the county to locate that line and confirm what rules apply to the proposed arrays, access roads and cable route. The current solar table lists A-1 and M-1 for non-shared utility-scale solar and leaves that entry blank for Agricultural Conservation (A-C).
In April 2025 the Board of Supervisors revised the prior solar ordinance to remove the general path for new utility-scale proposals and allowed three pending projects to continue through review. The ordinance that took effect in July 2026 replaced that prior ordinance. Start with the county’s current text, dated October 13, 2026, and ask which rules govern any older filing, approval or layout.
Sources Mecklenburg County zoning ordinance, § 7.1-26(C), utility-scale solar districts · Mecklenburg County zoning ordinance, § 1.3-1, effective date · Mecklenburg County zoning ordinance, § 5.1, official zoning map · Mecklenburg County Zoning, current ordinance, zoning districts and application forms · Mecklenburg County Board of Supervisors, April 14, 2025 minutes, item F.6
Use the last county action to set the next deadline
Under § 3.7-6(A), the same or a substantially similar special exception application cannot be reconsidered sooner than 12 months after a denial by the Board of Supervisors. The Zoning Administrator determines substantial similarity using the use and location, layout and intensity of the proposal. Bring both layouts and ask the county to confirm which ordinance applies to the filing and when the proposal can be reconsidered.
| Earlier project status | What to get before extending |
|---|---|
| Denied by the Board | Get the dated written decision and its reasons. Ask whether the current proposal is substantially similar and when the county can reconsider it. |
| Withdrawn early | Confirm the withdrawal date and whether the Planning Commission had made a recommendation. Section 3.7-6(B) sets a six-month reconsideration interval for the same or a substantially similar application withdrawn before a recommendation. If the Commission had already recommended denial, ask the county which timeline applies. |
| Complete before July 1, 2026, and still pending that day | Confirm with the Zoning Administrator when the filing was deemed complete and whether it awaited final action on July 1. Under § 1.3-5, review follows the rules in effect when the filing was accepted. The applicant can seek review under the replacement ordinance by withdrawing and filing anew. |
| Approved by the Board | Get the issued permit, approved plans, conditions and any written extension. Section 1.3-6 preserves covered prior approvals while valid. Ask whether the approval remains in force and whether it covers the changed layout. |
| Commission review only | Get the Planning Commission’s recommendation and ask whether the Board has since acted. If it approved the proposal, get the issued permit and its conditions. |
Sources Mecklenburg County zoning ordinance, §§ 3.7-4 and 3.7-6, permit validity and reconsideration · Mecklenburg County zoning ordinance, §§ 1.3-5 and 1.3-6, pending applications and prior approvals · Mecklenburg County zoning ordinance, § 3.7-3, application and decision
See what happened to 7 Bridges Solar
The Board allowed the pending 7 Bridges proposal to continue under its April 2025 action, then denied the special exception permit for the proposed 80-megawatt facility on May 12, 2025. The written denial cited the project’s farmland and forest impacts, construction traffic information and proximity to the South Meherrin River, among other reasons.
If a developer returns after a denial on your land, put the written reasons beside the new concept plan. Ask the developer to show which arrays, entrances or other features moved and what information it will provide to address the county’s concerns. Ask the county what filing and review the revised plan requires.
Sources Mecklenburg County Board of Supervisors, April 14, 2025 minutes, item F.6 · Mecklenburg County Board of Supervisors, May 12, 2025 decision on 7 Bridges Solar · Mecklenburg County zoning ordinance, § 3.7-3, application and decision · Mecklenburg County zoning ordinance, §§ 3.7-4 and 3.7-6, permit validity and reconsideration
Tie any option extension to records you can check
Take the county record and revised concept plan to your attorney with the proposed extension. If the developer needs more time to pursue a new decision, discuss which land it needs to hold during that period and which document should be in hand before a further extension, closing or long-term lease.
- Attach a dated exhibit showing the land the developer wants to hold, any separate access rights and the entrances you or your tenant need.
- Set dates for delivery of the county’s written decision on the new proposal and any permit with its plans and conditions. If more approvals are needed before entry or construction, identify them separately.
- Agree on the effect of a missed date or a layout that drops your land. Ask your attorney to address any release of an option memorandum or related access rights in the land records.
Common questions
Does the new zoning ordinance approve an old solar proposal?
Ask for the Board’s decision on the proposal and the permit issued for it. The current ordinance identifies the zoning districts where a special exception is available. The county still has to act on the application.
Can a revised layout come back sooner after a denial?
The county’s reconsideration interval applies to the same or a substantially similar application. Give the Zoning Administrator both drawings and ask for a determination on similarity and the earliest reconsideration date.
Does the county’s timeline extend my private option?
Look to the signed option and any amendments for extension rights, notice and payment requirements. Ask your attorney to compare those dates with the county’s review timetable.
Sources
- Mecklenburg County Zoning, current ordinance, zoning districts and application forms
- Mecklenburg County zoning ordinance, § 7.1-26(C), utility-scale solar districts
- Mecklenburg County zoning ordinance, § 1.3-1, effective date
- Mecklenburg County zoning ordinance, §§ 1.3-5 and 1.3-6, pending applications and prior approvals
- Mecklenburg County zoning ordinance, § 5.1, official zoning map
- Mecklenburg County zoning ordinance, § 3.7-3, application and decision
- Mecklenburg County zoning ordinance, §§ 3.7-4 and 3.7-6, permit validity and reconsideration
- Mecklenburg County Board of Supervisors, April 14, 2025 minutes, item F.6
- Mecklenburg County Board of Supervisors, May 12, 2025 decision on 7 Bridges Solar