Confirm the obligation and whether the event qualifies
Section 33 of the Milam lease applies after the Commencement Date. It ties relief to actual delay caused by an event outside the party’s reasonable control despite diligent efforts. Check the commencement record, what the party was due to do and how the event delayed that work.
The lease excludes financial inability and delays associated with labor shortages, supply chains or obtaining materials or equipment. It also excludes failure to apply for a required permit or approval, failure to provide required information on time and the tenant’s failure to approve contracts. Compare the facts with the full signed clause and its exclusions.

Track when the notice became due and what it says
Under Section 33(b), the party seeking relief must give written notice as soon as possible and no later than ten business days after it first knew or reasonably should have known of the potential force majeure event. The lease treats failure to give that notice as waiver of the right to an extension based on that event.
The notice must say whether the party claims the delay should be excused and explain its cause, expected length, steps to limit it and the timetable for those steps. The party must take reasonable measures to avoid or minimize the delay. Check Section 34(d) for delivery methods and keep proof of delivery with the notice.
Get the extension in writing for the affected obligation
After receiving the notice, Section 33(c) calls for the parties to meet, jointly determine how long the delay lasts and extend performance in writing for that period. Section 33(d) keeps each deadline separate. The landlord must show the cause of delay for each step or requirement it seeks to extend.
Compare the written extension with the original schedule and confirm the obligation, original date and revised date. If you are selling or assigning the property interest, give the closing team the signed documents and identify any requests still open.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss a property with an existing data center lease
Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, your proposed transaction and the next decision date. Keep signed leases, notices and schedules for private follow-up.
Questions landowners ask
What starts the Milam lease’s ten-business-day notice period?
Section 33(b) uses when the party first knew or reasonably should have known of a potential force majeure event. It requires notice as soon as possible within that limit.
Does a notice change a deadline on its own?
Section 33(c) calls for the parties to determine the delay period jointly and extend performance in writing. Check which obligation the written extension covers.
Does one extension apply to every deadline affected by the same event?
Section 33(d) treats deadlines separately and requires the landlord to show why each step or obligation it seeks to extend was delayed.
Sources & further reading
Sources checked November 21, 2026. The signed lease establishes the post-commencement notice and extension procedure. The reviewed filings leave any actual commencement, force majeure event, notice or extension unverified. Local rules and program details can change. Check the requirements for the actual project.