Maryland · Data centers

Can a large data center proceed on your Montgomery County, Maryland, land?

Sources checked

Check the zoning rule and the permit record

Montgomery County’s zoning ordinance bars projects that meet its Data Center definition in all zones it governs. The transition provision looks for a building permit received before August 17, 2026. A separate 18-month county moratorium, effective August 10, 2026, pauses the acceptance, review and issuance of building and grading permits for covered data centers. For either rule, start by confirming who governs your parcel and whether the qualifying building or group of buildings reaches 25 MW in actual or projected aggregate monthly electricity demand.

A buyer may show you a conditional-use approval or quote a power figure for the first building. Before giving the buyer more time under an option, ask for the demand figure for the full proposal and the county record of any building permit already issued.

Confirm who governs your parcel

Use the tax account number, parcel map and proposed site plan to locate each tract. Ordinance 20-35 applies to the part of the Maryland-Washington Regional District within Montgomery County. Montgomery Planning maintains the official zoning map for that area and identifies municipalities that keep separate maps, including Rockville, Gaithersburg and Poolesville.

If the plan crosses a municipal line, mark which side holds each proposed building and associated equipment. Ask Montgomery Planning and the municipality to confirm which zoning rules apply to each part. Check the permitting jurisdiction as well before relying on any county or municipal permit record.

Sources Montgomery Planning, official zoning map and municipal boundaries · Montgomery County Zoning Ordinance, § 59.3.1.6 use table

Check the electricity demand for the full proposal

The county’s zoning and permit laws both use a threshold of at least 25 MW of actual or projected aggregate monthly electricity demand for a building or group of buildings used for the specified data functions. Both definitions include associated infrastructure such as substations, backup generation, batteries and cooling equipment. They exclude facilities used primarily for manufacturing, quantum computing research, biomedical research or medical care, as well as higher education institutions approved to operate in Maryland by the Maryland Higher Education Commission.

Ask for the dated load estimate for the building or group of buildings, with phase-by-phase figures and the assumptions behind them. Suppose the buyer quotes 18 MW for the first building and its plan shows 32 MW of projected aggregate monthly demand for the full group. Ask the zoning and permitting offices to confirm which scope they will use and how they classify the proposal. For a sub-25 MW figure, ask which zoning classification and permits the proposed facilities would still need.

Sources Ordinance 20-35, § 59.3.5.2.B.1 data center definition · Signed Expedited Bill 19-26, § 1 building and grading permits

Match the issued building permit to the plan

The zoning use table lists no district that allows the defined Data Center use. Under § 4 of Ordinance 20-35, the prohibition applies to an application that had yet to receive a building permit from the Department of Permitting Services before August 17, 2026. Use the department’s permit status or data search tool, then ask for the actual issued permit and approved drawing set if the buyer relies on earlier approval. The amended ordinance also excludes the defined Data Center use from its Cable Communications System category. If the buyer cites an older approval under that label, ask for the decision, its approved plan and the agency’s determination for the current layout.

The separate permit law covers conditional-use applications filed before or after August 10, 2026, applications still under review, and approved applications for which the department has yet to issue a permit. If the status or scope is unclear, ask the department to confirm how both laws apply to the specific work in the buyer’s current plan.

Record the buyer citesWhat to verify
Conditional-use filing or written approvalAsk for the case number, decision and date. Check separately for any issued Department of Permitting Services building permit.
Grading permitVerify the number, issue date and covered work. Section 4 of the zoning ordinance specifies a building permit for its transition.
Building permit issued before August 17, 2026Verify when the applicant received it. Check the issuing office, permit status, address, approved scope and drawings. Ask whether revised plans or later phases need separate review or permits.

Sources Montgomery County Zoning Ordinance, § 59.3.1.6 use table · Ordinance 20-35, § 59.3.5.2.B.1 data center definition · Ordinance 20-35, §§ 4–5 building permit cutoff and effective date · Signed Expedited Bill 19-26, § 1 building and grading permits · Signed Expedited Bill 19-26, §§ 2–3 transition and sunset · Montgomery County Department of Permitting Services, permit status and records

Review option deadlines against the outstanding approvals

The signed permit law calls for an 18-month sunset measured from August 10, 2026. That points to February 10, 2028, subject to any later law. The zoning ordinance has its own building permit cutoff and gives the prohibition no sunset. If the buyer proposes to wait out the permit pause, ask for the zoning basis it expects to rely on once the pause ends.

Bring the written agency responses, current drawings and option agreement to your attorney. Check what evidence triggers an extension, whether the buyer can extend without your consent, and when the agreement releases the land if the required approvals are still outstanding. For a phased offer, identify the parcels tied up by each milestone and ask how unused tracts are released if the later phase stalls.

Sources Signed Expedited Bill 19-26, §§ 2–3 transition and sunset · Montgomery County Council, Bill 19-26 enactment record · Ordinance 20-35, §§ 4–5 building permit cutoff and effective date · Montgomery County Zoning Ordinance, § 59.3.1.6 use table

Common questions

Does heavy industrial zoning allow a large data center under Montgomery County’s zoning ordinance?

The use table bars the defined Data Center use across its districts, including industrial districts. If the buyer relies on the transition provision, ask for a building permit issued before August 17, 2026 and verify its scope with the Department of Permitting Services.

My buyer says it already has conditional-use approval. What should I ask for?

Ask for the written decision and the actual permit record for the project. Verify the type, issue date and scope of any permit with the department. The zoning transition specifically requires a building permit.

Can I rely on the projected end of the permitting pause in my land option?

Ask the county to confirm the current timing and what zoning rules would govern the proposal. Ask your attorney which agency records the agreement requires before another extension or closing.