Pennsylvania landowner guide

Which Pennsylvania DEP permit milestone should count in your data center land deal?

If a developer asks for more time to get a Pennsylvania data center permit, ask which activity needs approval and what stage its application has reached. The Pennsylvania Department of Environmental Protection (DEP) reviews individual activities such as land disturbance, emissions from on-site generators and wastewater discharges. Each approval can cover different work, parcels and phases.

Could my land work?

Ask the developer for the peak electric demand of the proposed campus, a dated list of permits by phase and the written status of each. For an application using the Governor’s Responsible Infrastructure Development (GRID) process, ask for the executed project-specific Consent Order and Agreement. Before agreeing to an option extension, closing or lease start, have counsel identify the agency decision and property exhibit that will satisfy the milestone.

Check which applications the order covers

Executive Order 2026-05 took effect August 18, 2026. The DEP review provisions in paragraph 1(b) and (c), published at 4 Pa. Code § 7.1082, apply to applications submitted after the effective date for data center projects with peak demand above 25 megawatts. Ask for the developer’s dated peak-demand estimate, including anticipated increases as the campus expands, and the filing date of each application. Ask DEP how the rules apply if the site has earlier filings or a revised layout.

Have the developer show which activities the applications cover and outline their locations on the land exhibit. Include access roads and other facilities crossing into another municipality where relevant. Ask for written confirmation of which municipalities must issue approvals and what DEP needs to document consistency with the local comprehensive plan.

Illustration of a landowner reviewing property plans

Identify whether DEP can review applications as they arrive

For the GRID review process, the developer identifies the project to DEP, gives notice of intent to comply, meets with DEP to discuss permits and local approvals, and signs a project-specific Consent Order and Agreement before submitting a new application. DEP reviews applications as they arrive. DEP can issue qualifying approvals on a rolling basis after it receives documentation of consistency with the local comprehensive plan and all required local or municipal approvals. That documentation also governs when the processing timelines for PAyback and the Permit Decision Guarantee begin.

For a covered application without an executed agreement, DEP starts review after receiving the local documentation and proof of any required water-withdrawal or wastewater-discharge authorization. DEP waits to issue any approval until it has received and reviewed all necessary applications. The PAyback and Permit Decision Guarantee programs are unavailable for that review. Ask DEP which approvals it is waiting for and whether the phase proposed for your parcel can proceed on the developer’s schedule.

Match the agency record to the parcel and phase

Ask for each authorization ID, the agency’s latest written status and any issued permit with its conditions and approved plans. DEP assigns an authorization ID when it accepts an application for review. The state permit tracker shows review steps and the final decision. Use its record to identify the applicant and permit, then check the dated decision and plans for the activity and parcel named in your agreement.

Compare the executed Consent Order and Agreement and its exhibits with the survey or lease exhibit. DEP’s model identifies the project site and acreage and includes terms for certain contracts with parties that will own, operate or use the facility. Have counsel review the executed terms before the buyer changes the acreage, phase, applicant or proposed developer.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Specify the written evidence for your deadline

If an option extension calls for a submitted application, identify the filing receipt and the application it must identify. If a sale closing or lease start depends on a permit, identify the issuing authority, the approval needed for the proposed work and any conditions that must be satisfied by that date. Decide what happens if the approvals cover only part of the property, a redesigned phase needs a new submission or DEP needs more time.

Sunland accepts data center land sale, lease and existing-agreement inquiries from owners and authorized representatives nationwide. Sunland may contract for a property and assign the agreement to a specialist developer. Share the general location, transaction type and decision date. Arrange private follow-up for detailed agreements and permit records.

Questions landowners ask

Can DEP review an application while local approvals are pending?

Under the GRID process, a proposal covered by the executive order can move through rolling review after the pre-application steps and signed Consent Order and Agreement. DEP needs the required local documentation before issuing a qualifying approval. For a covered application without an executed agreement, DEP waits for the local documentation and any required water-withdrawal or wastewater-discharge authorization before starting review.

Does a DEP authorization ID show that a permit has been issued?

DEP assigns the ID when it accepts the application for review. Look for the final decision in the tracker and ask for the issued permit and approved plans for the activity and phase that affect your land.

What if the developer adds another phase or changes applicants?

Ask DEP to confirm whether the same agreements and approvals cover the change, and have counsel check how the land agreement handles a revision before it triggers an extension, closing or lease start.

Sources & further reading

Sources checked November 22, 2026. Confirm the review process, permit conditions and approvals that apply to your parcels and development phase with DEP and the relevant municipalities. Local rules and program details can change. Check the requirements for the actual project.