What changed at the Cumulus Data Campus?
Amazon Web Services bought substantially all assets related to the campus and certain other assets in March 2024. Talen entered into a power purchase agreement with AWS in connection with the sale. In a separate proceeding, PJM proposed amending an interconnection service agreement with Susquehanna Nuclear and PPL Electric Utilities to increase the amount of co-located load covered from 300 to 480 megawatts. The Federal Energy Regulatory Commission rejected that amendment in November 2024. The figures describe the scope of the agreements before FERC.
In June 2025, Talen announced a revised agreement that called for delivery through the grid after transmission changes. Under that plan, Talen would supply the electricity to Amazon as its retail generation supplier, and PPL Electric Utilities would handle transmission and delivery. Talen subsequently reported that the transition to the revised power contract occurred in April 2026.

Ask how electricity would reach each phase
Ask the developer for a dated plan showing the site, where electricity would be delivered and where the facilities would connect to the grid. Ask for the initial delivery method and any fallback, including what service the project would have when the plant is offline. Compare the proposed routes with your survey so you can identify which crossings may affect land you plan to keep.
For each phase, ask for written confirmation of the customer, the proposed load and delivery date, and any limits on the service being offered. Ask which documents have been signed by the generator, electricity customer, utility or grid operator, which conditions are still open and who will pay for the work. A redacted status summary or review by your attorney can establish what the documents cover without circulating private commercial terms.
FERC and PJM have continued to address large-load and co-location rules in separate proceedings. Ask the utility and the project team which rules and approvals apply to the delivery method proposed for your site, and when they last confirmed that status.
Decide what a redesigned power plan would do to your deal
Ask your attorney to tie any deadline extension or payment condition to a dated document for the phase that affects your land. For an option, review the extension fee and when the acreage is released. For a lease, check when rent starts. For a sale, review whether the buyer can delay closing or change the price if the delivery plan changes.
Work through a specific fallback with the buyer. If grid delivery would need a wider utility corridor across land you plan to keep, ask who must approve that route, who pays for it and whether compensation will be negotiated separately. If the agreement expires, check when temporary access ends, who restores disturbed ground and which easements or other rights would continue.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landShare the land decision you face
Sunland accepts data center land sale, lease and existing agreement inquiries from owners and authorized representatives across the United States. Share the general location, approximate acreage, type of agreement and any decision deadline. Keep detailed electrical plans, private agreements and land records for a confidential review.
Questions landowners ask
Does a power purchase agreement tell me how electricity will reach the site?
Ask for the delivery method, the utility or grid operator’s written status and the outstanding work and approvals for each phase. The purchase contract identifies the supply obligation under its own terms.
What should I ask for if the buyer switches to grid delivery?
Ask for an updated service plan and a property map showing new routes and rights. Review the effect on extension dates, rent or closing payments and any land you plan to keep.
Sources & further reading
Sources checked November 19, 2026. The Cumulus disclosures describe a specific transaction. Ask the parties and the utility for written service status for your parcel. Local rules and program details can change. Check the requirements for the actual project.
- Talen’s September 2024 Form 10-Q, acquisitions and divestitures
- FERC’s November 2024 Susquehanna interconnection order
- Talen’s June 2025 announcement of the revised agreement, filed with the SEC
- Talen’s March 2026 Form 10-Q, AWS power purchase agreement glossary entry
- FERC’s June 2026 order on PJM co-located load
- PJM’s co-located load workshop and filing materials