Morro Bay, California · Battery storage
When does a Morro Bay battery storage site need voter approval?
Sources checked
A covered land-use change needs voter approval
Measure A-24 generally requires Morro Bay voter approval to change a Visitor-Serving Commercial or Commercial/Recreational Fishing designation on a parcel shown in Exhibit B. Before extending a battery storage land option, ask City Planning to check the proposed footprint against that map and confirm which battery storage rules apply. If the developer proposes the state opt-in process, ask for the California Energy Commission docket and the status of any separate coastal permit.
Vistra’s former power plant proposal shows why the distinction matters. Its 600-megawatt battery project proposed changing the battery site’s land-use designation from Visitor-Serving Commercial to General (Light) Industrial. Vistra later withdrew its City entitlement applications.
Check the parcel and the proposed land-use change
Morro Bay voters passed Measure A-24 in November 2024. Section 17.46.100 puts the voter approval step alongside the City’s ordinary amendment procedures. Ask City Planning to compare your assessor’s parcel number, legal description and project footprint with Exhibit B and the current General Plan and Local Coastal Program maps. The measure applies even if a covered parcel is subdivided and sets out limited exceptions. If a developer claims an exception or vested right, ask for the determination and records it relies on.
A separate temporary moratorium under Ordinance 670 covers new grid-scale battery facilities within city limits. The October 2026 staff report lists January 22, 2027 as its scheduled expiration. On October 27 the City Council adopted Ordinances 680 and 681 to prohibit front-of-the-meter storage, meaning storage that supplies the grid. Ordinance 680 takes effect upon California Coastal Commission certification. That certification was unconfirmed at the source check. Ordinance 681 calls for at least 30 days after adoption and any certification required by law. On November 22, the 30 days had yet to elapse. Ask City Planning which ordinance governs your proposed layout and when it applies.
Sources Measure A-24, ordinance text and Exhibit B map of affected parcels · Morro Bay Resolution 72-24, certified election result for Measure A-24 · Morro Bay Municipal Code §17.46.100, Ordinance 677 Exhibit C, page 3 · Plan Morro Bay, current zoning amendments and land-use map · Morro Bay project description, March 2024 draft environmental impact report filing · Morro Bay Ordinance 670, sections 3, 4 and 7 · Morro Bay City Council October 27, 2026 staff report, page 2 · Morro Bay City Council, October 27, 2026 minutes, item 7.a · Morro Bay Ordinance 680, sections 2–4 and 7 · Morro Bay Ordinance 681, sections 2 and 5
Verify the application before relying on its schedule
The City’s April 2025 response identifies the coastal development permit, conditional use permit and power plant property master plan applications for withdrawal. If a developer proposes state opt-in certification for an eligible project, the California Energy Commission can issue a certificate in place of local land-use approvals. The California Coastal Commission retains its permitting authority. Its staff’s August 2024 letter explains that the former power plant proposal would have needed a separate Coastal Commission permit on the state route.
| If the developer points to | Ask for this record |
|---|---|
| A local land-use change | The proposed designation and map, the City’s determination on Exhibit B and the status of any required voter approval. |
| A prior City application | The City file number, current status and latest decision. The Vistra applications identified by the City were withdrawn. |
| A proposed state opt-in filing | The Energy Commission docket number, the filed application and its current status. Ask Coastal Commission staff which separate coastal permit applies and request that file number too. |
Sources Morro Bay project description, March 2024 draft environmental impact report filing · City of Morro Bay, April 22, 2025 letter identifying the applications for withdrawal · California Coastal Commission staff letter on the Morro Bay project, August 2, 2024, pages 1–3 · California Energy Commission, Opt-In Certification FAQ and project list
Tie an option extension to a record you can check
If the developer asks for more time, agree on the document it must deliver and the date it is due. A filed application and an issued approval mark different stages. State which stage earns an extension, the payment due for the additional time and when the option expires if the developer misses the milestone or withdraws the application. Match each record to the parcel and footprint described in your option.
Sources Morro Bay City Council, October 27, 2026 minutes, item 7.a · City of Morro Bay, April 22, 2025 letter identifying the applications for withdrawal · California Energy Commission, Opt-In Certification FAQ and project list
Common questions
Would Measure A-24 apply to a parcel outside Exhibit B?
The voter approval provision is tied to the specified parcels and the covered designation changes. Ask City Planning to confirm the map boundary and the separate battery storage rules that apply to your proposal.
Did Vistra’s City withdrawal establish a new state application?
The City record confirms the local withdrawal. To establish a state filing for the same site, ask for its Energy Commission docket and check the application and its status there.
Sources
The voter measure and City records establish the local rules and the Vistra withdrawal. For a current proposal, verify effective ordinances and active applications with the responsible agencies.
- Measure A-24, ordinance text and Exhibit B map of affected parcels
- Morro Bay Resolution 72-24, certified election result for Measure A-24
- Morro Bay Municipal Code §17.46.100, Ordinance 677 Exhibit C, page 3
- Plan Morro Bay, current zoning amendments and land-use map
- Morro Bay project description, March 2024 draft environmental impact report filing
- California Coastal Commission staff letter on the Morro Bay project, August 2, 2024, pages 1–3
- City of Morro Bay, April 22, 2025 letter identifying the applications for withdrawal
- Morro Bay Ordinance 670, sections 3, 4 and 7
- Morro Bay City Council October 27, 2026 staff report, page 2
- Morro Bay City Council, October 27, 2026 minutes, item 7.a
- Morro Bay Ordinance 680, sections 2–4 and 7
- Morro Bay Ordinance 681, sections 2 and 5
- California Energy Commission, Opt-In Certification FAQ and project list