California landowner guide

Battery storage on your California property

Start with the property you could offer and the uses you need to keep. The developer should explain the rest using actual project records.

Could my land work?

Ask a California battery developer to identify the reviewing authority, electrical connection and land rights needed for the proposed site. Large eligible projects may choose the California Energy Commission’s opt-in route. That choice is separate from the utility connection and the agreement that determines your payments.

Describe what could be available

Send the county, nearby town and a road or address. If you know the parcel number, include it. You can still begin without one. Explain whether you would consider a lease, sale or either, and whether the whole property or a portion could be available.

Tell us what you need to keep using: a field, building, entrance, driveway, irrigation route or tenant area. If you intend to divide or develop the rest later, mention that too. Ask any project team to show retained uses alongside its proposed equipment.

An initial property inquiry does not require a finished plan or a guessed project size. A clear description of where the land is and what you want from an arrangement gives us a useful starting point.

Model landscape illustration of a parcel and its surrounding roads and terrain.

Ask which permit route applies

The CEC offers an optional certification route for eligible energy storage of at least 200 megawatt-hours. That is an energy measure, not a 200-megawatt power threshold. Ask the developer which route it intends to use and why.

For a project choosing that program, the CEC leads the environmental review. Its FAQ also identifies agency approvals that remain separate. Ask for a written list of the permissions still needed for the actual site, rather than assuming one certificate settles everything.

For other proposals, have the developer identify the applicable reviewing offices. Do not apply a large project’s route to a smaller proposal merely because both use batteries. Keep each decision, condition and approved drawing with the property records.

Reference: California Energy Commission: opt-in certification program and FAQ

Track the electrical connection separately

CAISO distinguishes interconnection to its transmission system from distribution interconnection handled through the utility. Ask which system the proposal would connect to, which utility is involved and what dated application or agreement supports that answer.

Request a short explanation of the work remaining: studies, upgrades, agreements and permission to operate. Who pays for each step, and what happens if the cost or timetable changes? An entry in a queue does not answer the payment questions in your land agreement.

If a cable or transmission route would leave your property, ask how the developer will obtain those rights. Include the route and construction access in the discussion before assuming the battery area is the only land affected.

Reference: CAISO: generator interconnection

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Read the project stage carefully

The CEC’s Potentia-Viridi page records Commission approval on May 26, 2026 and labels the project “Compliance - Pre-Construction.” Approval and current operation are different stages. Use the dated record, rather than treating a proposed-project list or announced completion target as proof that a facility is running.

For a proposal involving your property, ask for its own decisions and remaining conditions. A public example elsewhere does not establish eligibility, available connection capacity or a developer’s need for your land.

Keep the company’s construction target separate from the date your payments would begin. Ask what happens if the target moves after you have reserved the property.

Reference: California Energy Commission: Potentia-Viridi battery project

Ask what land is needed beyond your property

A battery site may depend on access or electrical routes across other land. Ask for one map that shows the equipment area, every road and cable route, and the parcels each route crosses. Who owns that land, and which permissions or agreements remain unfinished?

Riverside County’s Sapphire record provides a dated solar-plus-storage example. It describes private land for the solar and battery site, with access and electrical routes on federal land administered by the Bureau of Land Management. The November 2024 hearing notice also identifies county-road crossings. The project description separates those pieces rather than treating one private parcel as the whole project.

For your proposal, ask which route must be secured before construction can begin and what happens if it is delayed or unavailable. Could the company request a different entrance, more land or a longer option? Put those possibilities beside your payment and release dates. Sapphire’s documents do not establish permission or available capacity for another property.

Reference: Riverside County: Sapphire solar and battery project directory · Riverside County: November 25, 2024 Sapphire hearing notice · Riverside County: December 10, 2024 Sapphire Board submittal, item 21.2

Separate public development fees from your land payments

If a company shows you a development agreement with a county, ask what that agreement does. Sapphire’s December 2024 Board submittal describes a proposed county development agreement, public-benefit payments and other project fees. Those public obligations do not state the rent or sale price a private landowner would receive.

The same submittal recommends tentative permits subject to further steps, including the development agreement and final agricultural-contract cancellation. A recommendation is different from the Board’s vote, and tentative cancellation is different from a completed cancellation. Ask for the dated decisions that apply to your property and have your adviser explain any agricultural-contract obligations.

Keep a separate list of payments to you: option payments, extension payments, purchase price or rent, and compensation for access or damage. Identify the company responsible and the event that starts each payment. Do not use a county fee or the term of a public development agreement as a substitute for your private offer. The historical Sapphire documents reviewed here do not establish its current operating status or a new land-search mandate.

Reference: Riverside County: December 10, 2024 Sapphire Board submittal, item 21.2 · Riverside County: November 25, 2024 Sapphire hearing notice

Put the land rights and payments in writing

Ask for a map of the equipment area, roads, drainage, utility routes and temporary work space. Identify what stays available to you and what would be restricted. If the layout is unsettled, ask when the reserved area will be narrowed and unused land released.

List the proposed payments during investigation, extensions, construction and operation. What starts each payment? Who can extend the hold, for how long and at what cost? Have the draft and map reviewed together before committing the property.

Use the property form to ask Sunland about your land. California is selected on this page; you can correct it if needed. Contact details and location come first. Acreage and parcel number are optional.

Questions landowners ask

Does every California battery proposal use the CEC?

No. Ask the developer to identify the route for the actual proposal. The opt-in program is optional and has eligibility requirements.

Does 200 MWh mean 200 MW?

No. Megawatt-hours measure stored energy; megawatts measure power. Ask for both figures when comparing a project description.

What if the project needs a road or electrical route across other land?

Ask who must obtain those rights, which approvals remain and what a delay would mean for your option. Review the complete route map, not just the battery equipment area.

Are payments in a county development agreement my land rent?

They may describe public-benefit payments or project fees. Your private agreement should separately state what you receive, who owes it and when it starts.

Does a permit tell me when rent starts?

Your written land agreement should define the payment trigger. Compare it with the actual project milestones and possible delays.

Sources & further reading

Sapphire directory, dated hearing notice and selected Board-submittal sections checked October 7, 2026 for the two land-route/payment sections. They describe a solar-plus-storage proposal and staff recommendations; the final Board vote, federal right-of-way grant and operation were not established. Other California sources retain their October 6 review. Local rules and program details can change. Check the requirements for the actual project.