Nebraska landowner guide

Can you sell Nebraska land with a recorded solar participation option?

If a Nebraska solar participation agreement appears on your title report, get the signed documents before you agree to a closing date. Your parcel can be subject to a solar option or easement even when the project puts no equipment on it. A separate compensation agreement may govern payments.

Could my land work?

Match the recorded agreement or abstract to the signed documents, any written option exercise and any release. Ask title counsel to confirm the rights that will affect the buyer at closing. Check both the participation and compensation agreements for assumption, notice and payment terms before promising the buyer any future income.

Gather the recorded and private documents

Ask the county register of deeds and your title company for the recorded instrument, its legal description and any recorded amendments, assignments or releases. Compare the affected parcel with the deed and the land you plan to sell. Give counsel the signed agreement, its exhibits and any separate compensation agreement or notice from the solar company.

Nebraska Revised Statute § 66-911.01 requires a qualifying instrument or its abstract to be in writing and recorded and indexed in the county where the affected land is located. The statute allows the abstract to omit consideration, descriptions of planned improvements and decommissioning security or local requirements, and conditions for revision or termination. Ask counsel which statutory provisions apply to the interest and use the full agreement to fill in those details.

Illustration of a land parcel and surrounding landscape

Establish whether the option was exercised

Find the option’s effective date, the time available to exercise it and any extension. Ask for the written exercise notice, evidence it was delivered as required and the commencement date it specifies. If the parties say the option ended, ask counsel and the title company what evidence they need for closing and whether a release or other document should be recorded.

A recorded Cass County participation agreement, instrument 2024-00745, illustrates the difference. It gives the solar company five years to exercise by written notice, with the notice specifying when the easements begin. The option ends under its terms if it is unexercised when that period expires. The agreement identifies sunlight and project-effects easements and provides for their duration and potential renewal after commencement. Check your own record for those events and dates.

Confirm what the buyer will assume

Nebraska § 66-912.01 says a qualifying solar agreement runs with the land benefited and burdened and ends on the conditions stated in the agreement. Check the signed terms for obligations affecting the buyer, including restrictions on land use, any promises about project effects or applications, and any reserved uses. Ask counsel how the statute’s term and renewal provisions apply to the actual documents.

Section 10 of the Cass County example allows the owner to assign the participation agreement without the solar company’s prior written consent, subject to the buyer assuming its rights and obligations. Confirm the applicable transfer terms in your instrument. Put responsibility for any assumption, notices, signatures and recording on the closing schedule.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Document who receives each payment

Section 16 of the Cass County example refers to a separate compensation agreement that the parties agreed to keep unrecorded. Request that signed agreement and its amendments before valuing any income. Check who pays, what starts each payment, whether any amounts are outstanding and whether payment rights can be assigned or retained.

Provide the closing team with the payment history. Agree in writing who receives amounts already due, payments for periods that span closing and future installments. Have counsel identify any consent or assignment required under the compensation agreement and confirm who will send the payer any revised instructions.

Sunland welcomes nationwide inquiries about land sales, leases and existing solar agreements. Share the general location, your role and whether a participation option or easement affects the sale. Keep signed compensation agreements and payment records out of the initial inquiry.

Questions landowners ask

Does a recorded participation option mean the easement has started?

Check the agreement’s exercise terms and ask for the actual notice and the commencement date. Those records help establish which rights are in effect at closing.

Will the recorded document show what the buyer will be paid?

A qualifying Nebraska abstract can omit consideration, and payment terms can be in a separate agreement. Review that agreement and the payment history to determine what the parties can assign and what the buyer would receive.

Do I need the solar company’s consent to sell?

Have counsel check the actual agreement. The Cass County example allows assignment of the participation agreement without prior operator consent, subject to assumption. Review any separate compensation terms, required notices and title requirements as well.

Sources & further reading

The Nebraska statutes and the recorded Cass County agreement were checked November 20, 2026. The example illustrates the recorded terms. Confirm current title, any exercise or release, and the private payment terms for the property being sold. Local rules and program details can change. Check the requirements for the actual project.