Find out what interest is changing hands
Ask for a short before-and-after ownership chart with the legal names of the parties. Identify the company that owns the project, the party named in your agreement and the interest the buyer would acquire. Buying membership interests in a project company can leave the project company in place. An assignment of a lease, a sale of equipment and a deed to the land affect different interests. Ask for the documents that show which of those steps, if any, will accompany the purchase.
New York Public Service Law Section 70 generally calls for written Commission consent for a covered transfer or lease of a gas or electric corporation’s franchise, works or system, subject to exceptions. The Commission has applied a presumption of no full review to certain upstream ownership changes in lightly regulated electric companies, depending on market power and potential harm to captive ratepayers. Ask energy counsel how Section 70 and the applicable orders fit the exact transaction.

Match the ruling to the buyer and the deal
The Commission’s December 23, 2024 Holtsville ruling, Case 24-E-0378, concerned Savion’s proposed sale of all membership interests in Holtsville Energy Storage LLC to East Point Energy LLC. A February 4, 2025 erratum corrects the buyer name in the discussion. The Commission declined further Section 70 review for that specific transaction and directed the parties to notify its Secretary within 15 days after completion. That notice requirement came from the ruling.
On August 18, 2026, petitioners in Case 26-E-0553 described a separate proposed deal, with Savion still identified as the owner of all interests in the project company and Holtsville New Energy Ventures LLC named as the proposed buyer. The new petition sought its own ruling or approval and identified a positive Commission ruling as a closing condition. On November 20, 2026, the public index for the 2024 case showed no completion notice, and the index for the 2026 case showed no decision. Ask for the current docket and closing evidence if someone presents a ruling for a transaction today.
Check your own consent, notices and deadlines
Give counsel the complete signed option or lease, its amendments, any guaranty and any proposed consent, estoppel certificate or release. Check how the agreement treats a direct assignment and a change in who controls the signing company. Ask whether consent or notice is required, when a response is due and whether any guarantor or original party would be released. A state ruling resolves the regulatory question identified in that ruling. Your agreement governs the private obligations.
If your consent would take effect at closing, agree what evidence the project team will deliver and by when. That might include a dated notice of completion, a relevant docket filing receipt, and any assignment or replacement guaranty the agreement requires. Identify the person responsible for follow-up and how a delay affects your response or consent. Keep the final signed documents and the evidence you relied on together.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landBring the specific transaction to a property review
Sunland welcomes battery storage sale, lease and existing agreement inquiries from owners and authorized representatives across the United States. Share the property location, your role and which consent, signature or closing condition is under discussion. Keep unredacted agreements, ownership charts and supporting records for private review.
Questions landowners ask
Can I rely on a Section 70 ruling with the same project name but a different buyer?
Ask for the applicable case number and ruling for the actual transaction. The Holtsville ruling specified the transaction it addressed, and the later proposed buyer appeared in a separate case.
Does the ruling show that an ownership change has closed?
Check the actual closing evidence and any required follow-up filing. The Holtsville ruling called for a notice after completion.
Does a change in the project company’s owners require my signature?
Have counsel review the actual change-of-control, assignment and notice provisions and the document you were asked to sign.
Sources & further reading
Sources and public docket indexes checked November 20, 2026. The public records describe the regulatory proceedings and the parties’ proposals. For closing or consent, obtain the latest records and the private transaction documents. Local rules and program details can change. Check the requirements for the actual project.
- New York Public Service Law Section 70
- New York Public Service Commission Case 24-E-0378, declaratory ruling of December 23, 2024
- New York Public Service Commission Case 24-E-0378, February 4, 2025 erratum
- New York Department of Public Service, Case 24-E-0378 docket
- New York Department of Public Service, Case 26-E-0553 joint petition of August 18, 2026
- New York Department of Public Service, Case 26-E-0553 October 26, 2026 supplement
- New York Department of Public Service, Case 26-E-0553 docket