Find the rules and drawings for your project
Ask the developer for the case number and application receipt date. The current major renewable facility rules apply to applications the Office of Renewable Energy Siting and Electric Transmission received on or after March 9, 2026. For an earlier application, ask which rules and approved plans govern this work.
For a covered facility, 16 NYCRR §1101-2.15 requires agricultural maps to show agreed landowner development restrictions. It calls for an Agricultural Plan consistent with the two referenced Agriculture and Markets guidelines to the maximum extent practicable. Compare the approved plan and latest construction drawings with your parcel exhibit and any signed restrictions.

Separate restoration topsoil from excess material
Ask the contractor to mark topsoil stockpiles, where the saved soil will go back, and any subsoil or rock it expects to use as backfill. The October 2019 solar guidelines describe marking topsoil stockpiles on construction drawings and using saved soil for restoration. Get the dated drawings and ask who will review changes if field conditions require a different stockpile location.
For excess excavated subsoil and rock from areas intended to return to farming, the July 2025 guidelines call for removal from those areas and identify approved construction plans as the source for disposal locations. They exclude on-site disposal on active agricultural land used for crop production and call for material to leave the site when approved plans do not allow on-site disposal. The 2019 solar guidelines also identify landowner agreements, limits of disturbance and land-use approvals as factors in whether on-site disposal is allowed.
Check what the lease allows and what field records you will receive
If the plan calls for hauling material away, ask for the type, estimated quantity, destination and any needed approvals. Have counsel review the agreement for excavation, off-site removal, changes in scope and any agreed reporting or payment terms. If the work changes, ask who must approve a revised plan and what your agreement requires before the contractor proceeds.
Under §1101-3.4(ab), a covered permittee proposing temporary or permanent effects on land in agricultural production must retain an independent third-party agricultural monitor and implement the approved Agricultural and Drainage Remediation Plans. Ask who the monitor is and how to raise a concern. Discuss with the project team and farm operator what baseline photos, material records and restoration checks you can use to verify the condition of the field.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDescribe the proposed work when you inquire
Sunland welcomes nationwide inquiries from landowners and authorized representatives about land sales, leases and assignments of existing solar agreements. Share the general location, your role and the proposed work. Keep signed agreements and detailed farm and construction plans for private review.
Questions landowners ask
Can excess soil or rock stay on the site?
Check the approved construction drawings and where the material would go. The guidelines address disposal on active agricultural land and circumstances that require off-site disposal. Compare the proposed location with the permit and private agreement.
What if a contractor wants to move the topsoil stockpile?
Ask for a revised drawing showing the location, affected acreage and how the soil will be returned. Check the approved plan and signed agreement for the review and notice the change requires.
Do the guidelines set what I get paid for rock taken away?
Check the signed agreement and any amendments for payment terms tied to material removal. Ask counsel to review any proposed payment or reporting clause before agreeing to the work.
Sources & further reading
The current New York regulations and both incorporated agricultural guidelines were checked November 21, 2026. Confirm the actual application date, approved plans and signed land agreements before relying on proposed work. Local rules and program details can change. Check the requirements for the actual project.
- New York Department of Public Service, final 16 NYCRR Part 1101, agricultural resources and construction
- New York Department of Public Service, final 16 NYCRR Part 1100, effective date and incorporated guidelines
- New York Department of Agriculture and Markets, October 2019 solar construction mitigation guidelines
- New York Department of Agriculture and Markets, July 2025 construction mitigation on agricultural lands