When does a data center tenant owe a letter of credit after a rating change?

A data center lease can waive a tenant’s letter-of-credit requirement while the tenant or its guarantor meets the lease’s credit rating test. A signed Niagara Falls, New York, lease gives the tenant 30 days to deliver the letter of credit after the applicable entity ceases to qualify.

Could my land work?

Identify whose rating the lease uses and check the dated rating and outlook against the signed terms. If the exception ends, record the effective date of the change and the delivery deadline. Check the issuer, amount, form and expiry of the final instrument. Keep evidence that the landlord actually received it.

Check whose rating counts

Section 6.1 of the Niagara Falls lease waives the security deposit requirement while the tenant or its guarantor, if applicable, maintains the lease’s defined Investment Grade Status. Identify the tenant and any applicable guarantor in the signed lease and guaranty. Use dated rating-agency records for the entity whose status governs the exception.

Section 6.2 defines the required issuer or corporate family rating and calls for a stable or positive outlook. When all of the agencies named in the lease have rated the entity, at least two ratings must meet the test at the same time. Check the rating and outlook together, and identify the date on which any change became effective.

Illustration of a landowner reviewing property plans

Use the change date to track delivery

Section 6.1 measures the 30-day delivery period from the date the tenant or applicable guarantor ceases to meet the rating test. Record that date separately from the date you learn about the change or send a notice. Ask counsel to check any amendments or timing terms that affect your deadline.

The lease sets qualifications for the financial institution that issues the letter of credit and requires a standby instrument that is irrevocable and transferable. Confirm the issuer, beneficiary, amount, expiry and renewal terms against the signed agreement. Keep the issued instrument and record who received it and when. If the tenant proposes a surety bond, check the lease’s cap, financing restrictions and requirements for a compliant bond before counting it toward the security.

Check the guaranty and other credit-support provisions separately

Section 6.2 provides a separate process for releasing a tenant guaranty after the tenant qualifies, provides supporting documentation and receives the landlord’s written confirmation. If the tenant later loses the qualifying status after such a release, Section 6.2 gives it 30 days after the landlord’s written notice to provide a replacement guaranty. Check the applicable test, trigger and evidence for each obligation.

Section 6.3 separately addresses a minimum credit rating and possible additional security after written notice if neither the tenant nor guarantor meets that separate minimum for the period specified in the lease. The public exhibit redacts some of those terms. If you are selling property or assigning a lease, give counsel the current signed documents, any notices and the latest security records so the parties can identify which obligations are open and who will handle them.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Discuss a data center sale, lease or existing agreement

Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, the transaction you’re considering and your next decision date. Keep rating records, signed leases and security instruments for private follow-up.

Questions landowners ask

Does the landlord’s notice start the Niagara Falls letter-of-credit deadline?

Section 6.1 starts the 30-day period when the applicable tenant or guarantor ceases to meet the lease’s rating definition. The separate guaranty replacement clause uses the landlord’s written notice.

Can a surety bond count toward the required security?

The lease allows a qualifying surety bond to cover part of the requirement, subject to a cap and the landlord’s financing documents. Review the signed terms and confirm receipt of the final instrument before relying on it.

What records show the landlord received the required security?

Keep the final issued letter of credit, evidence of delivery and the signed lease or amendment showing the form and amount required. Verify the beneficiary, issuer, effective dates and renewal terms.

Sources & further reading

Sources checked November 21, 2026. The signed lease’s public exhibit redacts amounts and certain conditions. The filings reviewed leave any credit trigger, actual instrument, delivery and lease commencement unverified. Local rules and program details can change. Check the requirements for the actual project.